SECTION 2 - INSTALLATION
II. VENTILATION SYSTEM
|
|
| IMPORTANT |
ENGLISH |
| Where national or local codes require the | |
|
| installation of fire suppression equip- | |
|
|
| |
|
| ment or other supplementary equipment, | |
|
| DO NOT mount the equipment directly to | |
|
|
| the oven. |
|
|
| MOUNTING SUCH EQUIPMENT ON |
|
|
| THE OVEN MAY: |
|
|
| |
|
| • | VOID AGENCY CERTIFICATIONS |
|
| • | RESTRICT SERVICE ACCESS |
|
| • | LEAD TO INCREASED SERVICE |
|
|
| EXPENSES FOR THE OWNER |
|
|
|
|
|
| A. | Requirements |
CAUTION
•A mechanically driven ventilation system is REQUIRED for gas oven installations.
•A mechanically driven ventilation system is STRONGLY RECOMMENDED for electric oven installations.
PROPER VENTILATION OF THE OVEN IS THE RESPONSIBILITY OF THE OWNER.
B.Recommendations
NOTE THAT THE HOOD DIMENSIONS SHOWN IN FIGURE 2- 2 ARE RECOMMENDATIONS ONLY. LOCAL AND NATIONAL CODES MUST BE FOLLOWED WHEN INSTALLING THE VENTILATION SYSTEM. ANY APPLICABLE LOCAL AND NATIONAL CODES SUPERSEDE THE RECOMMENDATIONS SHOWN IN THIS MANUAL.
The rate of air flow exhausted through the ventilation system may vary depending on the oven configuration and hood design. Consult the hood manufacturer or ventilation engineer for these specifications.
To avoid a negative pressure condition in the kitchen area, return air must be brought back to replenish the air that was exhausted. A negative pressure in the kitchen can cause heat- related problems to the oven components as if there were no ventilation at all. The best method of supplying return air is through the heating, ventilation and air conditioning (HVAC) system. Through the HVAC system, the air can be
NOTE: Return air from the mechanically driven system must not blow at the opening of the baking chamber. Poor oven baking performance will result.
C.Other ventilation concerns
•Special locations, conditions, or problems may require the services of a ventilation engineer or specialist.
•Inadequate ventilation can inhibit oven performance.
•It is recommended that the ventilation system and duct work be checked at prevailing intervals as specified by the hood manufacturer and/or HVAC engineer or specialist.
18"
458mm
Fig. 2-2 - Ventilation System
2"/51mm minimum
18"
458mm
12" | 3" |
305mm | 76mm |