NAP-200-003

Sheet 6/12

Installation of Main Equipment

2.19-INCH RACK-MOUNTING INSTALLATION

(1)When the system is two PIM configuration, connect PIMs with three bolts as shown in Figure 003-1.

(2)Before mounting the PIM, connect the TOP COVER, BOTTOM COVER and AC CORD-A-U to the PIM as shown in Figure 003-3and Figure 003-4.

(3)Secure the 19” BR ACKET (H) to the 19-inch Rack as shown in Figure 003-5A

(4)Mount the PIM on the 19” BR ACKET (H) as shown in Figure 003-5B . Then, secure the PIM to the 19” BR ACKET (H) as shown in Figure 003-5C .

 

 

19-INCH RACK (IEC)

19” BRACKET(H)

 

 

PIM

19” BRACKET(H)

 

 

 

BOTTOM COVER

 

 

B

 

 

 

A

 

C

 

 

 

PIM

 

FRONT

 

 

Figure 003-5

Mounting PIM to 19-Inch Rack

 

 