NAP-200-006

Sheet 2/2

Cable Running to MDF

2.CABLE RUNNING TO EXTERNAL MDF

(1)Bring the MDF cable up to the Main Equipment through the cable hole(s) of the bottom cover.

(2)Connect the champ connector of each MDF cable to an LTC connector located on a PIM using the screws provided, as shown in Figure 006-2.

(3)Pare the sheath of each MDF cable and secure the shield to the bottom of the PIM using tie wraps, as shown in Figure 006-2.

 

LTC CONNECTOR

 

PBX

 

 

 

CHAMP CONNECTOR

 

PIM

 

 

 

MDF

 

 

CABLE

 

 

TIE WRAP

 

 

PIM

 

 

25-30 mm

 

 

(1.0-1.2 inch)

 

 

SHIELD

 

FRONT

 

TO MDF

 

 

Figure 006-2

Cable Running to External MDF

 

 

NDA-24219

CHAPTER 3

Page 49

Revision 2.0

Page 63
Image 63
NEC NEAX1000IVS system manual Cable Running to External MDF