226 MG 1000B platform hardware installation
5Place the MG 1000B Core on the guide brackets. Carefully slide the
MG 1000B Core into the rack until the ear brackets come to rest
against the rack support.
6Use the four remaining #12-24 self-tapping screws to fasten the MG
1000B Core to the rack supports (two screws on eachside).
7Make sure that the back of the MG 1000B Core is on the guide
brackets. See Figure 71 "MG 1000B Core and MG 1000B Expander
installed in a rack" (page 226).
Figure 71
MG 1000B Core and MG 1000B Expander installed in a rack
8Install the equipment ground wires for the MG 1000B Core, MG
1000B Expander, and Signaling Server. See Communication Server
1000E: Installation and Configuration (NN43041-310).
9Install a UPS (if required) according to the manufacturer’s
instructions.
10 Open the MG 1000B Core and install the Software Daughterboard,
Security Device, and ground clip as described in Communication
Server 1000E: Installation and Configuration (NN43041-310).
11 Install circuit cards in the MG 1000B Core and the MG 1000B
Expander. See Communication Server 1000E: Installation and
Configuration (NN43041-310).
12 Make the Ethernet connections. Configure the Ethernet port to
enable TM 3.01 and Element Manager connectivity as required.
a. See Procedure 22 "Connecting the Ethernet ports" (page 247).
Nortel Communication Server 1000
Branch Office Installation and Commissioning
NN43001-314 01.02 Standard
Release 5.0 20 June 2007
Copyright© 2007, Nor tel Networks
.