Complete the following checklist before installing the unit.

ο1. Clearances

Allow adequate space for free air circulation, service clearances, piping and electrical connections, and any necessary ductwork. For specific unit dimensions, refer to the submittals. Allow clearances according to local and national electric codes. See the following section on “Service Access” and refer to Figure 3 on page 12 for recommended service and operating clearances. Provide removable panels for concealed units.

ο2. Structural Support

The floor should be strong enough to adequately support floor mounted units. The installer is responsible to supply adequate support rods for installation of ceiling units.

ο3. Level

If necessary, prepare the floor or ceiling to ensure the unit installation is level (zero tolerance) in both horizontal axis to allow proper operation.

Set the unit level using the chassis end panels as a reference point. Do not use the coil or drain pan as the reference point since the coil is pitched and the drain pan has an inherent positive slope to provide proper drainage.

ο4. Condensate Line

A continuous pitch of 1 inch per 10 feet of condensate line run is necessary for adequate condensate drainage.

ο5. Wall and Ceiling Openings Recessed units only:

Refer to the submittal for specific dimensions of wall or ceiling openings before attempting to install the unit.

Horizontal concealed units only:

The installation of horizontal concealed units must meet the require- ments of the National Fire Protection Association (N.F.P.A.) Stan- dard 90A or 90B concerning the use of concealed ceiling spaces as return air plenums.

ο6. Exterior

Touch up painted panels if necessary. If panels need paint, sanding is not necessary. However, clean the surface of any oil, grease, or dirt residue so the paint will adhere. Purchase factory approved touch up epoxy paint from your local Trane Service Parts Center and apply.