Olicom 9600 manual Phase Check, Proceed with Cryopump Power Phase Switch Setting

Page 29

Installation

CTI-CRYOGENICS

HELIX TECHNOLOGY CORPORATION

Phase Check

WARNING

Follow all high voltage safety precautions when performing this procedure to prevent the possibility of electrical shock.

1.Make sure power is applied to compressor circuit as described in Table 1-2.

NOTE: The circuit breaker will trip immediately during step 2 if the power phase connections are not correct.

2.Turn the Compressor circuit breaker to the ON position. If the circuit breaker trips, refer to step 3. If the circuit breaker does not trip, refer to step 4.

3.If the circuit breaker trips, perform the following steps:

a.Turn the Compressor circuit breaker to the OFF position.

b.Disconnect the power cord from the power source.

c.Remove the circuit breaker terminal cover.

d.Reverse the wiring order of Compressor circuit breaker terminals X and Y.

e.Torque the circuit breaker terminal screws to 12 in.-lbs.

f.Install the circuit breaker terminal cover.

g.Repeat steps 1- 2 of this procedure.

4.Install the rear panel.

5.Proceed with Cryopump Power Phase Switch Setting.

3-6

P/N 8040540

Image 29
Contents 8040540 Rev 12/2004 Compressor Installation, Operation, Maintenance InstructionsHelix Page Table of Contents Operation InstallationMaintenance Figures Tables 9600 Compressor Description Compressor ConfigurationsGeneral BenefitsCTI-CRYOGENICS Helium Refrigeration System System Documentation9600 Compressor Dimensions SpecificationsCompressor Weight WeightElectrical Input Specifications ElectricalCooling Water Cooling Water SpecificationsGeneral General Compressor Operating Specifications9600 Compressor Rear View Component Locations Component DescriptionPower Inlet Power on IndicatorSystem Circuit Breaker Control Circuit BreakerCooling Water OUT Return Gas CouplingCryopump Electrical Outlet Cryopump Electrical Outlet Pin AssignmentsCompressor Remote Connector Cryopump Power Phase SwitchCompressor Remote Connector Pin Assignments Multiple On-Board Cryopump Connections9600 Compressor Connected to Multiple On-Board Cryopumps 9600 Compressor Connected to Multiple Cryo-Torr Cryopumps Multiple Cryo-Torr Cryopump ConnectionsCTI-CRYOGENICS Introduction Unpacking and InspectionShipping Carton Inspection Removal from Shipping CartonCompressor Inspection Shipping Carton ContentsCompressor Helium Static Pressure VerificationInstallation END Flexible Water Lines Supply and Return Water Line ConnectionsHard Water Lines Electrical Connections Power Cable Preparation9600 Compressor Circuit Breaker Terminals Cover Removed Proceed with Cryopump Power Phase Switch Setting Phase CheckConnecting Connecting/Disconnecting Helium Flex LinesCryopump Power Phase Switch Setting Disconnecting Single On-Board Cryopump Connections Single On-Board Cryopump ConnectionsSingle Cryo-Torr Cryopump Connections Single Cryo-Torr Cryopump InstallationHelium Line Connections Power Cable Connections Multiple Cryo-Torr Cryopump Connections CTI-CRYOGENICS Recommended Multiple Cryo-Torr Cryopump Installation Alternative Multiple Cryo-Torr Cryopump Installation Operation Adjusting System Helium PressureStatic Helium System Pressure Verification 9600 Compressor Helium Static ChargeCompressor Operation Replacement of Helium Circuit Components CTI-CRYOGENICS Suggested Maintenance Equipment MaintenanceScheduled Maintenance Disconnecting Self Sealing Couplings Adsorber ReplacementDate 9600 Compressor Helium Pressure Control Components Reducing Helium PressureAdding Helium Increasing Helium PressureCTI-CRYOGENICS Product Information Appendix a Customer Support InformationMail Page Figure B-19600 Compressor Flow Diagram Appendix B Flow DiagramAppendix B Flow Diagram Technical Inquiries Appendix C Troubleshooting ProceduresTroubleshooting the Compressor Compressor Remote Table C-1 Compressor Troubleshooting ProceduresAppendix a to contact CTI-CRYOGENICS Appendix D Schematic Figure D-19600 Motor Drive Compressor Schematic