3-50
Cisco MGX 8800/8900 Series Hardware Installation Guide
Releases 2 - 5.2, Part Number OL-4545-01, Rev. H0, May 2006
Chapter3 Preparing for Installation
Site Requirements for a MGX 8830 or MGX 8830/B Switch
CESM-8T1/B 29.1
RJ48-8T1 3
R-RJ48-8T1 3
FRSM-2CT3 49
BNC-2T3 5
FRSM-2T3E3 30
BNC-2E3 and
BNC-2E3A
5
BNC-2T3 5
FRSM-8E1 25.84
MGX-RJ48-8E1 3
RJ48-8E1 3
R-RJ48-8E1 3
SMB-8E1 5
R-SMB-8E1 5
FRSM-8E1-C 25.84
MGX-RJ48-8E1 3
RJ48-8E1 3
R-RJ48-8E1 3
SMB-8E1 5
R-SMB-8E1 5
FRSM-8T1 25.84
RJ48-8T1 3
R-RJ48-8T1 3
FRSM-8T1-C 25.84
RJ48-8T1 3
R-RJ48-8T1 3
FRSM-HS2/B 46.4
12IN1-8S 2
SCSI2-2HSSI/B 15
MPSM-8-T1E1 36.3
RJ48-8T1 3
R-RJ48-8T1 3
Table3-20 Power Consumption Calculation for Cisco MGX 8830 or MGX 8830/B Switch
Components (continued)
Front Card
ABCD
Number of Cards
Installed
Watts Per Card Total Card
Power
(AxB)
Total 48V Current
(ADC)
(C/48)