5-100
Cisco MGX 8800/8900 Series Hardware Installation Guide
Releases 2 - 5.2, Part Number OL-4545-01, Rev. H0, May 2006
Chapter5 Installing the Cisco MGX Switch or Gateway
Installing the MGX 8830 or MGX 8830/B Switch
Note After completing these steps, proceed to the “First Time Power On Procedure for MGX Switches”
section on page 5-137 if this is a first-time installation.
Step5 Install the AC Power Supply Tray
Remove the AC Power Supplies from the AC Power Supply Tray
Install the AC Power Supply Tray(s)
Reinstall the AC Power Supplies
Connect the Console Port
Step6 Install the Cisco MGX 8850
Switch without a Mechanical Lift
Prepare for Installation
Remove the Front Car ds
Remove the Back Cards
Remove the Back Cards from
an APS Assembly
Remove the DC PEM(s )
Install the Switch in the Rack
or Cabinet
Reinstall the APS Assembly
Reinstall the Back Cards
Reinstall the DC PEM(s)
Reinstall the Front Cards
Install the Cisco MGX 8850
Switch with a Mechanical Lift
Install the Switch in a 19-Inch
or 23-Inch Rack
Install the Switch in a 19-Inch
Cabinet
Connect Power to the Cisco MGX
8830 Switch
Connect AC Power to the
Switch
Connect DC Power to the
Switch
Step7 Install the Cable Management Assembly Connect the External Clock
(optional)
Step8 Connect the AC Power Supply Tray to the Cisco MGX 8830 Switch Connect the Alarms
Step9 Connect the Back Cards Connect the MP Connection
Step10 Connect the Console Port Connect the LAN1/2 Ports
Step11 Connect Power to the Cisco MGX 8830 Switch
Connect AC Power to the Switch
Connect DC Power to the Switch
Verify EMI Compliance
Step12 Connect the External Clock (optional)
Step13 Connect the Alarms
Step14 Connect the MP Connection
Step15 Connect the LAN1/2 Ports
Step16 Verify EMI Compliance
Table5-7 Installation Checklist—MGX 8830 System (continued)
Check Steps
Rack-Mounted System
(WithoutLift) Rack-Mounted System (with Lift) Cisco Cabinet System