Hardware installation
IFor PRIMECENTER Racks and DataCenter Racks:
The mounting of the rails in the different racks is described in the next sections. Installation of the cable management is described in detail in the Technical Manual for the respective rack.
IFor 19-inch standard rack (for the Japanese market):
For information on mounting of the rails in the
3rd party racks
Certain general conditions must be met:
–Installation dimensions (see the dimensions shown in figure 3 on page 51):
1 Front of rack
2 Rear of rack
A Rack depth (comparison PRIMECENTER Rack 940/1000/1100 mm)
B Rack width (comparison PRIMECENTER rack 700 mm)
C Clearance for 19" installation level C1 Front 19" installation level
C2 Rear 19" installation level
D Cable routing area (cable area depth) and ventilation
E Space for front panel and ventilation
F Space for right and left support systems
P PRIMERGY rack installation depth a1 Front left support upright
a2 Front right support upright
b1 Rear left support upright
b2 Rear right support upright
50 | Operating Manual | TX200 S6 |