sealed lead acid batteries outside the United States, go to http:// www.ibm.com/ibm/environment/products/batteryrecycle.shtml or contact your local waste disposal facility.
20. Install the RAID controller, as shown in Figure 77.
f10ug033
Figure 77. Installing a new RAID controller
a.Slide the RAID controller all the way into the empty slot.
b.Close both levers until the latch locks into place.
21.Install the SFPs and then connect the
22.On the DS4100
23.On the DS4100 base storage server, wait approximately one minute and then use the DS4000 Storage Manager client to place the controller in online state (it was placed offline in step 6 on page 106).
24.If the operation fails, repeat the command. If the operation fails again, reseat the controller and repeat this step.
Note: Note that on all DS4100 models, it might take 15 minutes to a few hours for a new battery to become fully charged. The DS4000 Storage Manager client will show the battery as failed until it is fully charged. Controller caching is automatically disabled until the new battery becomes fully charged.
25.Use the DS4000 Storage Manager client to monitor the status of the storage server and to reset the battery age.
Note: On the DS4100 base storage server, there are two cache batteries in
the unit (one for each controller). Make sure that you reset the age for the correct battery.
108IBM TotalStorage DS4100 Storage Server: Installation, User’s, and Maintenance Guide