Panasonic R410A service manual TEST RUN 6-1.Preparing for Test Run, Test run, Fig

Models: R410A

1 198
Download 198 pages 33.93 Kb
Page 190
Image 190
6. TEST RUN

6. TEST RUN

6-1. Preparing for Test Run

Before attempting to start the air conditioner, check the following:

(1)All loose matter is removed from the cabinet espe- cially steel filings, bits of wire, and clips.

(2)The control wiring is correctly connected and all electrical connections are tight.

(3)The protective spacers for the compressor used for transportation have been removed. If not, remove them now.

(4)The transportation pads for the indoor fan have been removed. If not, remove them now.

(5)The power has been supplied to the unit for at least 5 hours before starting the compressor. The bottom of the compressor should be warm to the touch and the crankcase heater around the feet of the com- pressor should be hot to the touch. (Fig. 6-1)

(6)Both the gas and liquid tube service valves are open. If not, open them now. (Fig. 6-2)

(7)Request that the customer be present for the trial run.

Explain the contents of the instruction manual, then have the customer actually operate the system.

(8)Be sure to give the instruction manual and warranty certificate to the customer.

(9)When replacing the control PCB, be sure to make all the same settings on the new PCB as were in use before replacement.

The existing EEPROM is not changed, and is connected to the new control PCB.

6. Test run

ON

6. Test run (Power must be turned ON at least 5 hours before attempting test run)

Power mains switch

Fig. 6-1

Liquid tube

Gas tube

 

Fig. 6-2

6

6-2

Page 190
Image 190
Panasonic R410A service manual TEST RUN 6-1.Preparing for Test Run, Test run, Fig