GETTING STARTED

M102E/M501 TRS

GETTING STARTED

(Addendum to M101E Manual - P/N 04740 Rev A)

3. GETTING STARTED

3.1. Unpacking the M102E

Unpack the M102E as per the directions ins Section 3.1 of the M101E Manual - P/N 04740 Rev A.

1. There are no shipping screws to be removed in the M102E.

3.2. Unpacking the M501-TRS

2.Inspect the shipping package for external damage. If damaged, please advise the shipper first, then Teledyne Instruments.

3.Carefully remove the top cover of the converter and check for internal shipping damage.

Remove the screws fastening the top cover to the unit (four per side).

Lift the cover straight up.

CAUTION

Never disconnect electronic circuit boards, wiring harnesses or

electronic subassemblies while the unit is under power.

4.Inspect the interior of the instrument to make sure all components are in good shape and properly seated.

5.Check the connectors of the various internal wiring harnesses and pneumatic hoses to make sure they are firmly and properly seated.

6.There are no shipping screws to be removed in the M501-TRS.

7.Replace the top cover.

NOTE

The M501-TRS will not operate properly with the top cover removed.

The air cooling required to stabilize the temperature of the converter tube is dependent

on air flow patterns that only exist with the top cover in place.

Without the top cover in place, the thermal cutout may overheat and shut off the

heating element.

05514 Rev A1