BioOptix™ 10
Appendix B Fluid Path Diagrams
B-3
Manual injections do not operate the pump. The system pauses
for the operator to turn the Mode valve to the Manual Inject
position. The liquid sample is then forced through the injection
port on top of the BioOptix 10 system. The liquid sample is intro-
duced directly onto the column (Figure B-4).
Figure B-4 Fluid path for Load-type blocks -
Manual injections
B.3 Gradient-type Blocks Gradient blocks are similar to fluid-type blocks (Figure B-5). The
Buffer valve switches between buffers A and B to produce the
correct mix.
Figure B-5 Fluid path for Gradient-type blocks
Mode
Effluent
To Fox y
Manual Sample Injection
Column
Buffer
Sample
Channel Mode
Effluent
Pump
To Waste To Foxy
Buffer A Buffer B
Column