7.1 Daily Check

1.Zero calibration and span calibration

1.Perform zero calibration. For the calibration procedures, refer to Section 6.8.1 Zero calibration.

2.Following the zero calibration, perform a span calibration. For the calibration procedures, refer to Section 6.8.2 Span calibration.

3.Zero/span calibration should be carried out once a week, or as required.

2.Flow rate check

1.Sample and purge gas flow rates are as follows:

Sample gas flow :

0.5L/min ± 0.2L/min

Purge gas flow :

About 1L/min

2.Instrument checks and maintenance should be carried out every day, as required.