NDIR Gas Analyzer

Maintenance

 

 

 

7. Maintenance

7.1 Daily Check

1.Zero calibration and span calibration

1.Perform zero calibration. For the calibration procedures, refer to Section 6.8.1 Zero calibration.

2.Following the zero calibration, perform a span calibration. For the calibration procedures, refer to Section 6.8.2 Span calibration.

3.Zero/span calibration should be carried out once a week, or as required.

2.Flow rate check

1.Sample and purge gas flow rates are as follows:

Sample gas flow :

0.5L/min ± 0.2L/min

Purge gas flow :

About 1L/min

2.Instrument checks and maintenance should be carried out every day, as required.

Teledyne Analytical Instruments

75

Page 91
Image 91
Teledyne 7500ZA Daily Check, Ndir Gas Analyzer Maintenance, Zero calibration and span calibration, Flow rate check