Installation

Model 7500ZA

 

 

 

 

 

 

3.1 Installation Conditions

To install the analyzer for optimum performance, select a location that meets the following conditions;

1.This instrument is designed for rack mounting in a standard 19” equipment rack.

2.Indoor use only.

3.Vibration-free.

4.Free of dust and debris and obstruction around the analyzer.

5. AC power:

100V to 240 VAC

Operating voltage:

85V to 264V AC

Rated frequency:

50/60 Hz

Power consumption:

100 VA max.

6.Operating conditions:

Ambient temperature : -5° to 45°C (max. 40°C when two optical units are used, and the power supply is more than 200V AC)

7.Maintenance space:

When analyzer is installed by itself, adhere to the diagram to make sure there is adequate space to remove the cover for maintenance.

When the analyzer is installed as an unit, See Section 3.2.1

8.A circuit breaker that meets IEC60947-1 and IEC60947-3 specifications should be installed.

9.A breaker should be installed near the analyzer where an operator can access it.

10.A label that clearly identifies the breaker should be visible.

11.The breaker rating should meet the analyzer rating max 2A and conform to all necessary approvals.

3.2 Installation

3.2.1 Installation of Analyzer Main Frame

Installation methods for the analyzer main unit is shown below.

Teledyne Analytical Instruments

8

Page 24
Image 24
Teledyne operating instructions Installation Conditions, Installation Model 7500ZA, Installation of Analyzer Main Frame