Final Tests

Chapter 7 Basic SCE 2000 Platform Operations

Starting the SCE 2000 Platform

Final Tests

The procedures for performing the final tests to verify that the SCE 2000 is functioning properly are explained in the following sections:

Verifying Operational Status (on page 7-3)

Viewing the User Log ("Viewing the User Log Counters" on page 7-3)

Verifying Operational Status

After all the ports are connected, verify that the SCE 2000 is not in a Warning state.

To verify that the SCE 2000 is not in a warning state, complete the following steps:

Step 1 On the SCE 2000 Front panel, examine that the Status LED is flashing green.

Step 2 To display the operation status of the system, at the SCE 2000# prompt, type show system operation-statusand press Enter.

A message displaying the operation status of the system appears. If the system is operating in order, the following message appears:

System Operation status is Operational.

EXAMPLE:

The following example displays a sample output where the LEDs appear red/orange:

SCE 2000#show system operation-status

System Operation status is Operational

Viewing the User Log Counters

View the user log for errors that occurred during the installation process.

To display the user log device counters, complete the following steps:

Step 1 At the SCE 2000# prompt, type show logger device User-File-Log counters and press Enter.