14 Push the two levers (green) towards each other to disengage with the lower locking holes and lift them up until they engage with the two upper locking holes.

15 Connect the two relay connectors on the roller ASY.

16 Close the upper transport

unit. (See page 4-2)

Pad Replacement Replace the pad as follows:

WARNING

Wait at least 3 minutes after turning off the power before replacement.

Upper transport unit

Operator panel

Power switch

Lever

Lever (green)

Roller ASY

1Turn off the power switch. Make sure that the hopper table is at the bottom.

2Open the upper transport unit. (See page B-2)

3Disconnect the two relay connectors on the roller ASY.

4Push the two levers (green) towards each other to disengage with the upper locking holes and lower down the two levers until they engage with the two levers locking holes.

4-38

M3099EX/EH OEM Manual