Preparing for installation

Before you install the DS3200 storage subsystem, create a detailed plan of how this unit will be used in your storage configuration. The plan should include determining RAID levels, failover requirements, operating systems that are to be used, and total storage capacity requirements.

To prepare the DS3200 storage subsystem for installation into a rack cabinet, complete the following steps:

1.Prepare the site to meet all area, environmental, power, and site requirements. For more information, see “Specifications” on page 13.

2.Move the shipping box that contains the DS3200 to the site.

CAUTION:

or

>18 kg (39.7 lb)

or

18-32 kg (39.7-70.5 lb)

The weight of this part or unit is between 18 and 32 kg (39.7 and 70.5 lb).

It takes two persons to safely lift this part or unit. (C009)

3.Make sure that you have the correct host software for your operating system.

The support CD that comes with the DS3200 has the correct IBM DS3000 Storage Manager Version 2 host software.

The CD also includes the DS3000 storage subsystem controller firmware. For the latest controller firmware, see http://www.ibm.com/servers/storage/support/ disk/.

4.Read the applicable readme files that are included in the Storage Manager host software or DS3200 controller firmware packages for any updated information about hardware, software, or firmware products.

5.Continue with “Required tools and hardware.”

Required tools and hardware

Have the following tools and equipment available:

vRegion-specific power cords that are required for the DS3200

v5/16 (8 mm) hex nut driver

v#0 and #1 Phillips screwdrivers

vElectrostatic-discharge protection (such as a grounding wrist strap)

vEthernet interface cables and cable straps

20System Storage DS3200 Storage Subsystem: Installation, User’s, and Maintenance Guide

Page 38
Image 38
IBM DS3200 Storage Subsystem manual Preparing for installation, Required tools and hardware