Power-off overview

Review the following information before you continue with the power-off procedure:

Turn off the power to each device according to the following shutdown sequence:

1.Turn off power to the host before the storage subsystem. If the host must stay powered-on to support a network, see the operating-system documentation for information about disconnecting the storage subsystem logical drives from the host before the storage subsystem is powered-off.

2.Turn off power to the storage subsystem before you turn off power to the storage expansion enclosures. Turn off both power-supply switches on the rear of the storage subsystem.

3.Turn off power to other supporting devices (for example, management stations).

Note: You do not have to perform this step if you are servicing only the storage subsystem.

To turn off power to one or more storage subsystems for a planned shutdown, complete the steps in the following procedure. To turn off power for an unplanned shutdown, see “Restoring power after an unexpected shutdown” on page 57. Figure 33 on page 47 shows the locations of the power switches on a storage subsystem.

Before you proceed, use the Storage Manager software to determine the status of the system components and special instructions. The operating-system software might require you to perform other procedures before you turn off the power.

1.Stop all I/O activity to each storage subsystem.

2.Determine the status of all storage subsystems and components in the configuration by completing the following steps:

a.Check all LEDs on each component in the storage expansion enclosures. Make sure that all the LEDs show normal status.

b.Check all LEDs on each component in the storage subsystem. Make sure that all the LEDs show normal status.

c.Review the status of the configuration in the Subsystem Management window by clicking the Summary tab.

The status is either Optimal or Needs Attention.

3.Do the LEDs indicate normal operation, and is the status Optimal on all configuration components?

v Yes: Go to step 5 on page 57.

v No: Go to step 4.

4.To diagnose and correct the fault, complete the following steps:

a.Run the Recovery Guru by clicking Recovery Guru in the toolbar in the Subsystem Management window.

b.Complete the recovery procedure.

If the Recovery Guru directs you to replace a failed component, use the individual LEDs to locate the failed component.

56System Storage DS3200 Storage Subsystem: Installation, User’s, and Maintenance Guide

Page 74
Image 74
IBM DS3200 Storage Subsystem manual Power-off overview