01201138 | 0107 | 16 | 9 | |
Notice | Date | Page | ||
9. Installation |
INSTRUCTION
HANDBOOK
Installation of the exhaust of burn gas
Connect the whole set of pipes on your cheminey pipe, that is to say :
•1 aluminium pipe (A) lenght 500 mm (20") on the exchanger.
•1
•1 aluminium pipe (A) length 500 mm (20") .
•1 draught accelerator (D).
It is necessary to install the gas ex- changer at the ground level.
D0693A
Evacuation of burn gas from a machine with gas heating must never be connected to the evacuation used for a dry cleaning machine or other ma- chine of the same type.
Installation of the chemney regulator
For a correct running of the installation, this chimney regulator must always have its axle of rotation of his fl ap perfectly horizontal.
The adjustment toothed wheel has to be positioned on the mark no 7.
D0435