D0410

B

AC

D

0107 17 9

Notice Date Page
01201138
INSTRUCTION
HANDBOOK 9. Installation
Gas connection
CAUTION
The installation, connection and gas arrival adjustments for the machine
must be done by qualifi ed personnel only.
The customer must install a fi lter and a manual stop valve on the supply side of the ma-
chine if NATURAL GAS is used.
For BUTANE 28-30 mbar or PROPANE 37 or 50 mbar, the customer must install a fi lter, a
manual closing valve and a pressure reducer.
Check that the diameter of injectors is adequate for the king of gas of your installation (see
table). The machine is delivered with extra injectors in a plastic envelope. There is also a sheet
metal plate with a cork joint or an adjusting head to feed the machine with another gas.
Connect the installation at the exchanger : DN 20 (3/4" BSP).
A : gas burner B : ignition and control electrodes
C : ignitor D : injectors
E : gas admission