Chapter 4: Preparing for Router Installation

Site Preparation Checklist

The checklist in Table 40 on page 75 summarizes the tasks you need to perform when preparing a site for Services Router installation.

Table 40: Site Preparation Checklist

Item or Task

Performed By

Date

Notes

Verify that environmental factors such as temperature and humidity do not exceed router tolerances.

Measure the distances between external power sources and the router installation site.

Select the type of rack.

Plan the rack location, including required space clearances.

Secure the rack to the floor and the building structure.

Acquire appropriate cables and connectors.

Site Preparation Checklist 75

Page 99