Preparing for Router Installation

Before installing a J-series Services Router, make sure that your site has the proper operating environment and equipment. Use the checklist at the end of the chapter to help you prepare your site.

This chapter discusses the following topics:

General Site Guidelines on page 63

Rack Requirements on page 64

Router Environmental Tolerances on page 66

Fire Safety Requirements on page 66

Power Guidelines, Requirements, and Specifications on page 67

Network Cable Specifications on page 74

ISDN Provisioning on page 74

Site Preparation Checklist on page 75

General Site Guidelines

The following precautions help you plan an acceptable operating environment for your Services Router and avoid environmentally caused equipment failures:

For the cooling system to function properly, the airflow around the chassis must be unrestricted. Ensure that there is adequate circulation in the installation location. In J2320 and J2350 routers, allow at least 6 in. (15.2 cm) of clearance between the left and right sides of the chassis and adjacent equipment. In J4350 and J6350 routers, allow at least 6 in. (15.2 cm) of clearance between the front and back of the chassis and adjacent equipment.

Follow ESD procedures described in “Preventing Electrostatic Discharge Damage” on page 201, to avoid damaging equipment. Static discharge can cause components to fail completely or intermittently over time.

Install blank PIM panels in empty slots, to prevent any interruption or reduction in the flow of air across internal components.