Fuji Labs ZSP Airtightness test, Setting of temperature inside locker, Warm-up time

Page 14

6.4Airtightness test

(1)Piping inside panel

Since airtightness is confirmed during tests before shipment, an Airtightness test during trial run is usually unnecessary. When a long time has passed after shipment, then carry out the following proce- dure.

(a)Close the drain port.

(b)Connect standard gas to the sample gas inlet.

(c)Connect the transparent tube of the conditioner air suction port (see Fig. 10-1) vertically (in place of a manometer).

(d)Flow standard gas gradually, and after reaching a pressure of about 1961Pa, close the needle valve of the pressure regulator.

(e)Check the water level at the air suction port of the conditioner, and if the drop in the level in less than 147Pa/min, then the error due to insufficient airtightness is negligible.

(f)If a leak is present when measuring a harmful gas, make a check by applying soapy water to the normal pressure section while aspirating outside air.

(2)Piping outside panel

Thoroughly check the tightened condition of pipe joints. If necessary, apply pressure from the extrac- tor outlet side and make a test as in the preceding item (1).

(3)If the airtightness is insufficient, make a test on each section, find the faulty location and make it completely airtight. If the faulty location is before the aspirator, then air enters the gas pipe midway to cause a drop in the indication.

6.5Setting of temperature inside locker

Turn on power supply to a space heater depending on the ambient temperature. Ventilation fan should always be turned ON.

6.6Warm-up time

Turn ON the auto breaker.

(1)Gas extractor

Turn ON the power switch and warm up the extractor for at least 1 hour.

(2)Heating pipe (option)

Turn ON the power supply auto breaker of heating pipe and warm up the pipe for at least 1 hour.

(3)Electronic gas cooler

Turn ON the power switch and warm up for at least 10 minutes.

(4)NO2/NO converter (option)

Turn ON the switch, set the temperature regulator at 220° C, and warm up for about 30 minutes until indication of the temperature reaches 220± 2° C. 200° C for a NO/CO (+ O2) analyzer

(5)Analyzer

Turn ON the power switch and carry out warm-up. Infrared gas analyzer: about 8 hours

Zirconia O2 sensor: about 30 minuets

– 6 –

Image 14
Contents Infrared GAS Analyzer Introduction RequestProhibition Iii Prohibition Others Contents Vii Composition SpecificationsOutline PreparedSelection of gas sampling location InstallationSelection of installation site Installation work Connection of cablesPiping procedure Description of Each Part Injection of clean waterSupply of external power Preparation for OperationWarm-up time Setting of temperature inside lockerAirtightness test INDICATION/OPERATION Panel SO2Function and indication of indication/operation panel This panel consists of the following functionsAdvice on Operation General operation of indication/operation panelPreparation of standard gas CalibrationKinds of standard gas Pressure regulation for standard gas cylinder Calibration concentration setting except zirconia O2 sensor Func CAL SET ENTCAL Calibration concentration setting zirconia O2 sensor CAL Comp ENT Zero Single-component analyzer Auto calibration Auto CAL Func Auto CAL Func Auto CAL ENT Auto calibration ON/OFF setting Func Hold ENT Operating procedure OperationMaintenance Routine maintenance and inspectionConditioner Centration is measured in the setting range of 0 to Periodic maintenance and inspectionOther maintenance and inspection 200ppm or more at 0.5L/minMaintenance of sampling device Gas extractor type ZBAK1Membrane filter Exploded view of diaphragm type aspirator Structure of electronic dehumidifier Structure of NO2 /NO converter Structure of Permapure dryer Maintenance of zirconia O2 sensor Others, major component figuresStandard Accessories and Spares Standard accessoriesSpares for 1 year optional Code for preparation of 1-year spares and suppliesProcessing of Heating Pipe Ends OutlineEnd processing method Grid 300mm 40mm Grid area 150 mm Check after piping Clamp supportSpecifications of tube trace Specifications of heating pipeTroubleshooting Troubleshooting of instrumentError codes and remedies Power consumption Ambient temperaturePower supply Mass weightNumber of output points and kinds of outputs Standard requirements For sample gasMonth/NO2, 100ppm Block diagram Moving average outputCalibration tolerance Automatic calibration output hold Automatic calibrationOrdering information Calibration cycle Once/day variable, up to 7 daysCode Symbols Diaglam Functions of individual components For outdoor installation type For indoor installation typeConnection Diagram Only specified outputs are wiredHead Office Instrumentation Div International Sales Dept