Fuji Labs ZSP instruction manual Structure of electronic dehumidifier

Page 40

(5)Check and maintenance of electronic gas cooler

(a)Fan motor

This motor should be replaced periodically every 20,000 hours (about 2 years in case of continuous operation ) as a standard though this varies with operating condition. However, if no abnormality cannot be found at the time of a periodic replacement, the motor is further usable continuously.

(b)Gas passage cleaning procedure

When bubbling has come to diminish significantly, it can be thought that the passage has come to be clogged by dust, etc.

In this case, the gas passage needs be cleaned in the procedure given below.

INLET joint

C

OUTLET INLET

L

B

Spiral pull-out device

Spiral guide

Heat exchanger

A

DRAIN

(i)When looking at the inside of INLET joint, area B of the spiral guide can be seen. In the area B, a lateral hole of 1.5mm dia. is bored. So, insert the top of the furnished spiral pull-out device into the hole as shown below and extract the spiral guide.

(ii)Clean the gas passage and spiral guide. For detergent, use a one having a chemical composition which will not affect hard glass, hard PVC, polyethylene and fluoro- rubber. After washing, rinse adequately with water and dry the inside well by blowing compressed air.

(iii)When inserting the spiral guide to the original position, it should be pressed lightly until area A of the spiral guide comes in contact with the bottom. As a standard, area B of the spiral guide should be located with a distance L of about 15 to 20mm from the top face C of INLET joint. Note that attention should be paid since piping is stepped.

Note) For sampling with the pressure control valve, clean the gas passage using the above procedure when the sample flow begins to be extremely reduced.

Fig. 10-5 Structure of electronic dehumidifier

– 32 –

Image 40
Contents Infrared GAS Analyzer Introduction RequestProhibition Iii Prohibition Others Contents Vii Specifications OutlineComposition PreparedSelection of installation site InstallationSelection of gas sampling location Installation work Connection of cablesPiping procedure Injection of clean water Supply of external powerDescription of Each Part Preparation for OperationAirtightness test Setting of temperature inside lockerWarm-up time INDICATION/OPERATION Panel SO2Function and indication of indication/operation panel This panel consists of the following functionsAdvice on Operation General operation of indication/operation panelKinds of standard gas CalibrationPreparation of standard gas Pressure regulation for standard gas cylinder Calibration concentration setting except zirconia O2 sensor Func CAL SET ENTCAL Calibration concentration setting zirconia O2 sensor CAL Comp ENT Zero Single-component analyzer Auto calibration Auto CAL Func Auto CAL Func Auto CAL ENT Auto calibration ON/OFF setting Func Hold ENT Operating procedure OperationMaintenance Routine maintenance and inspectionConditioner Periodic maintenance and inspection Other maintenance and inspectionCentration is measured in the setting range of 0 to 200ppm or more at 0.5L/minMaintenance of sampling device Gas extractor type ZBAK1Membrane filter Exploded view of diaphragm type aspirator Structure of electronic dehumidifier Structure of NO2 /NO converter Structure of Permapure dryer Maintenance of zirconia O2 sensor Others, major component figuresStandard Accessories and Spares Standard accessoriesSpares for 1 year optional Code for preparation of 1-year spares and suppliesProcessing of Heating Pipe Ends OutlineEnd processing method Grid 300mm 40mm Grid area 150 mm Check after piping Clamp supportSpecifications of tube trace Specifications of heating pipeTroubleshooting Troubleshooting of instrumentError codes and remedies Ambient temperature Power supplyPower consumption Mass weightMonth/NO2, 100ppm Standard requirements For sample gasNumber of output points and kinds of outputs Block diagram Moving average outputAutomatic calibration Ordering informationCalibration tolerance Automatic calibration output hold Calibration cycle Once/day variable, up to 7 daysCode Symbols Diaglam Functions of individual components For outdoor installation type For indoor installation typeConnection Diagram Only specified outputs are wiredHead Office Instrumentation Div International Sales Dept