Multiquip MQP30GM, MQP20IZ Mechanical Installation NEW Battery, Dry Charged Batteries, Cables

Page 53

MECHANICAL INSTALLATION — NEW BATTERY

Dry Charged Batteries (continued)

After electrolyte is added, check the open circuit terminal voltage of the battery. If a 12-volt battery reads less than 10 volts, this is an indication of either a reverse cell, an "Open" circuit, or a shorted cell, and the battery should be replaced.

When a dry charged battery has been activated and not put into service, it must be maintained, handled, and kept charged like any other wet battery.

Charged and Moist Batteries — Activation

The activation characteristics of the charge and moist batteries differ from conventional dry charged batteries in initial fill level, specific gravity readings, and initial testing procedures.

These batteries are activated the same as dry charged batteries except each cell is filled to the bottom of the vent well. It is only necessary to let it stand 10 minutes after electrolyte is added. The specific gravity will typically fall to a range of 1.200 to 1.230 (corrected to 80°F [26.7°C]). This does not indicated low performance capability. After several days of charge and discharge in normal vehicle service, the specific gravity will rise and level out at a full charge value of 1.245 to 1.255.

To determine the performance capability of these batteries during initial activation, they should be given a load test following the 10 minute soak period.

The battery should not be load tested unless the electrolyte temperature is at least 60°F (15.5°C). Apply a test load equal to 1/2 the cold cranking performance at 0°F (-17.8°C). Read the voltage at 15 seconds and remove the load. If the battery temperature is 70°F (21°C) or higher and the voltage reading is 9.6 volts or more, the minimum required voltage is 9.5 for 12-volt batteries.

If the voltage readings are below the minimum values, charge the battery at a slow charge rate and retest. If the battery fails the second test, reject it.

Removing Old Battery

Before removing the old battery, carefully note the location of the positive battery terminal and mark the polarity on the positive cable. By doing this, you will avoid installing the new battery reversed (which could damage the electrical system). Remove the ground cable connector first. This precaution will avoid damage to wiring, and/or the battery, by accidental "grounds" with tools.

Use the proper size box, or pen end wrench, when removing battery cables.

Inspect the battery tray for possible damage or corrosion. Be sure the tray and hold-down are mechanically sound and free from corrosion. Corroded parts may be cleaned with water (to which some household ammonia or baking soda has been added) and scrubbed with a stiff brush. Cleaned parts should be dried and painted. Do not paint the battery or terminals. Clean and tighten the ground connection. Tighten the starter relay and starter connections too.

Cables

Battery cables must carry large starting currents with a minimum loss of voltage, since engine cranking speed is dependent on the voltage available at the starting motor.

Examine the cables to ensure the insulation is intact and the terminal connectors and bolts are not corroded. Replace all unserviceable parts. Also consider replacing cables that have temporary terminal ends bolted on. Temporary or emergency terminals should be replaced with new cables as soon as possible. As the acid corrodes terminals and cables, their resistance increases and the voltage loss between the battery and the starter increases. This increase in resistance due to corrosion also restricts the flow of charging current to the battery. This condition will eventually cause the battery to become undercharged and the plates will become sulfated.

Installation

Be sure the battery has been charged as described in this section. If using an MQ Power battery, charge the battery as described in the low water-loss battery installation on page 56 if needed.

Make sure the battery is level in the battery rack. Be sure there are no foreign objects lying in the tray that may cause damage to the bottom of the battery container. The hold- down should be tightened snugly, but not to the point where the battery cracks or distorts.

Figure 17. Typical Electric Starter Motor Connections

INDUSTRIAL GENERATOR SETS — APPLICATION & INSTALLATION MANUAL — REV. #4 (09/07/07) — PAGE 53

Image 53
Contents Application & Installation Manual MQ PowerPage Heres HOW to GET Help Table of Contents Page Foryour Safety and the Safety of Others Safety Message Alert SymbolsAccidental Starting Safety Message Alert SymbolsGeneral Safety Important Safety InstructionsGeneral Safety Radiator Important Safety InstructionsMaintenance Safety Operation SafetyEmergencies Always know the location of the nearest fire extinguisherBattery Safety Genset should be inspected regularly for fire hazards Fire ProtectionAlways drain fuel prior to lifting Lifting the Generator SetIntroduction Always remember Safety FIRST!!! Safety involves twoIntroduction About This ManualInstallation Application and InstallationOverview ApplicationCold Climates and Derating Factors Installation OverviewLocation Outdoor LocationsGenset Sizing Procedure „ Static Uninterrupted Power Supplies UPSGenset Sizing Generator Set Sizing CalculationsStep Sequence Guidelines 765.7 Repeat steps a and b as necessary through all the worksheets Running load should not be Generator Set Sizing Calculations Select a Generator SetEstablish the minimum size required Single-Phase Induction Motor Genset Sizing Determining Load CharacteristicsDetermining Load Characteristics Lighting Calculate SkVA as follows Genset Sizing Determining Load CharacteristicsThree-Phase Induction Motors Calculate SkW as follows Determining Load CharacteristicsFull SkVA 100201 Three Phase Nema Motor Code TableVariable Frequency Drives Synchronous MotorsStatic UPS Equation above Output kVA is the nameplate kVA capacityRadiator discharge air high frequency sound Noise ConsiderationNoise Laws and Regulations Noise Zones Peak DayEnvironmental Considerations dBA Comparison Chart dBABelow estimates the noise level from multiple noise sources Adding Additional Sound SourcesDistance Effects on dBA Effects of DistanceFollowing will help reduce structure-borne noise Reducing NoiseSee on page 32 for typical measures in reducing noise Following will help reduce airborne noiseReducing Noise Acoustic MaterialMounting Access to SetMounting on a Slab Floor Mounting on a Sub-Base Fuel TankMounting Foundation Mounting FoundationVibration Isolators Mountingthe Generator SETGeneral Information Mounting Vibration Isolators Installation and Adjustment ProcedureFuel System Installation Mechanical Installation Fuel System DieselDiesel Fuel Supply TankMechanical Installation Fuel System Diesel Minimum Fuel Supply / Return Hose and Pipe Sizes Diesel Fuel SupplyMechanical Installation Fuel System Gaseous Fuels Gaseous Fuel Supply Mechanical Installation Fuel System Gaseous FuelsContaminants Natural GAS Schedule 40 Iron Pipe Sizing Pipe and Tube SizingTypical Pipe Schematic for Propane Vapor Distribution Liquid Propane Schedule 40 Iron Pipe Sizing Mechanical Installation Fuel SystemAdditional references include Fuel Storage RegulationsEnvironmental Protection Field Installing a Generator Exhaust System Mechanical Installation Exhaust SystemExhaust System Installation Mechanical Installation Exhaust System Condensation Trap Factory Recommended Engine Exhaust Silencers Exhaust System Installation Reference DataPurpose of the Battery Mechanical Installation Battery SystemMQ Power Batteries How BatteriesWorkEngine Starting System Mechanical Installation Battery System„ See the Battery Safety Instructions on New Battery Installation Mechanical Installation NEW BatteryPreparation of Charged and Wet Batteries Preparation of Dry Charged Charged and Moist BatteriesRemoving Old Battery Mechanical Installation NEW BatteryDry Charged Batteries Charged and Moist Batteries ActivationBatteryTesting Battery System -TESTING BatteryStep One 1 -Visual Inspection See Flow Chart, on next Step Three 3 Load ProcedureBattery Testing Chart Battery System Batterytesting ChartCharging LowWater-loss Batteries Battery System Charging BatteryBattery Storage Battery System Battery Charger FC & FCA Battery Charger Battery System Battery ChargerLC1224-500-2 Battery Charger FC1224-10-2011U Battery ChargerBattery Charger Safety Battery System Battery Charger SafetyBattery Charger Installation Engine Cooling Mechanical Installation -VENTILATION and CoolingVentilation and Cooling Vents and DuctsLouvers Mechanical Installation -VENTILATION and CoolingFactory Mounted RadiatorVentilation Mechanical Installation Mounted Radiator CoolingRadiator Set Requirements Mechanical Installation Mounted Radiator CoolingMounted Radiator Cooling System Remote Radiator Cooling optional Mechanical Installation Remote Radiator CoolingRemote Radiator Cooling Mechanical Installation Remote Radiator CoolingHot Well Installation Mechanical Installation Hotwell Cooling19,200/60x8 = 40 gpm Mechanical Installation Heat Exchanger CoolingHeat Exchanger Coolant Heaters Coolant TreatmentCoolantTreatment Electrical Installation DC Controlwiring Control Box DC Control Wiring Control BOX Back PanelControl box contains the following „ Digital Control Module „ Control Box Back Panel ComponentsL3 3 PH DC Controlwiring Control BOX Back PanelGenerator Set Wire Diagram AC Electrical Connections Transfer SwitchConnection Of Generator Leads For Correct Voltage Output AC Electrical ConnectionsMounted fuel tank is used, the electrical stub-up Electrical TerminationsBreaker Line circuit breakerAC Electrical Connections System Grounding Pole ATS AC Electrical Connections System GroundingEquipment Grounding AC Electrical Connections Equipment GroundingElectrical Distribution System Electrical Distribution SystemPRE-START Preparation Run the Generator Set PRE-START PreparationAppendix Installation Checklist Appendix MAIN-LINE Circuit Breaker For MQ Power Industrial GeneratorsAppendix MAIN-LINE Circuit Breaker MQ Power Industrial Generator Specifications Appendix Generator SpecificationsAppendix Generator Specifications MQ Power Industrial Generator Specifications Appendix Engine Specifications MQP175IV MQP200IV MQP250IV Appendix Engine SpecificationsGenerator Model MQP300IV MQP350IV MQP400IV Generator Model MQP30GM MQP45GM MQP60GM MQP80GM MQP100GM Appendix Engine SpecificationsMQ Power Generator Dimensions & Weights Appendix Dimensions and WeightsMQ Power Generator Dimensions & Weights Appendix Dimensions AndweightsHeres HOW to GET Help