Multiquip MQP45GM, MQP20IZ, MQP40IZ, MQP60IV, MQP50IZ, MQP30GM, MQP30DZ AC Electrical Connections

Page 74

AC ELECTRICAL CONNECTIONS

Emergency Standby Generator Systems (600 Volts and below) The National Electric Code (NEC) requires the engine-generator be provided with phase overcurrent protection such as fuses or circuit breakers. In some applications, ground fault protection may be also be required.

Generator Main Line Circuit Breaker

a)Generator-Mounted Main Line Circuit Breaker (MCB) - Industry practice is to provide a molded-case circuit breaker, sized to protect the generator feeder conductors against overcurrent, and provide provisions for a disconnecting means, to meet National Electric Code (NEC) requirements.

b)Neutral Conductors – The ampacity of the neutral conductor is generally permitted to be equal to or greater than the calculated maximum single-phase unbalance of the load. Where a significant portion of the load is non- linear, the neutral conductor should be sized in accordance with anticipated neutral current but never less than 100 percent rated.

Sizing A Generator Main Line Circuit Breaker

Sizing a generator main line circuit breaker is typically the result of electrical engineering review of generator load schedules and design calculations for a feeder and its overcurrent device, keeping in mind that the primary purpose of the generator main line circuit breaker is to protect the feeder conductors as per the National Electric Code (NEC).

MQ Power offers several factory-mounted circuit breaker options per model, based on generator output voltage and current ampacity. Unless specified otherwise, these circuit breakers, both thermal-magnetic and electronic trip types, are factory sized for the maximum output current of each engine-generator, with regards to their respective voltage connection. The circuit breakers are mounted on the engine-generator so as to meet code requirements which stipulate the overcurrent protective device be located within 25-feet of the generator output terminals.

It should be noted too, when sizing a main line circuit breaker, that feeder ampacity and overcurrent device ratings should be calculated by summing the total of load currents of all branch circuits being supplied by the engine-generator, multiplied by any applicable demand factors allowed by National Electric Code (NEC). In any event, the minimum size of the generator main line circuit breaker should be at least equal to the ampacity rating of the feeder conductors (or the next largest standard rating).

Field Installing A Generator Main Line Circuit Breaker

All work should be completed by qualified persons familiar with the installation, construction and operation of generator sets. All work should be completed in accordance with the National Electric Code (NEC), Uniform Building Code (UBC) and other state or local codes.

DO NOT attempt to field install a main line circuit breaker while the engine-generator is capable of starting and running. Serious injury or death could result. Make sure the generator control is in the OFF position, then disconnect the engine starting battery by lifting the cables (ground cable first). It is advisable to use "Lock-Out" tags accordingly.

When installing a main line circuit breaker NOT factory supplied by MQ Power, it is code required that the circuit breaker be UL listed. The overcurrent protective device should be installed with the correct voltage, current and short-circuit interruption ratings that are appropriate for the generator output. The interrupting capacity of the circuit breaker must be equal to or greater than the amount of fault current that can be delivered at the point in the system where the circuit breaker is applied.

Once the circuit breaker has been properly sized and the appropriate cable and lugs have been determined, the circuit breaker should be mounted on the engine-generator in a suitable location.The circuit breaker should be mounted on the engine-generator so as to minimize vibrations produced by the engine while running.

Connection Of Generator Leads For Correct Voltage Output

It is required of the installer to connect the generator main stator leads (12-lead generator) in a configuration required to meet the system voltage output requirement. Refer to the MQ Power reconnection diagram to review the various voltage connection configurations. Once the voltage selection and correct wiring configuration has been completed, the wiring is terminated at the circuit breaker input lugs and/or bus bar.

PAGE 74 — INDUSTRIAL GENERATOR SETS — APPLICATION & INSTALLATION MANUAL — REV. #4 (09/07/07)

Image 74
Contents MQ Power Application & Installation ManualPage Heres HOW to GET Help Table of Contents Page Safety Message Alert Symbols Foryour Safety and the Safety of OthersSafety Message Alert Symbols Accidental StartingImportant Safety Instructions General SafetyImportant Safety Instructions General Safety RadiatorEmergencies Operation SafetyMaintenance Safety Always know the location of the nearest fire extinguisherBattery Safety Fire Protection Genset should be inspected regularly for fire hazardsLifting the Generator Set Always drain fuel prior to liftingIntroduction Always remember Safety FIRST!!! Safety involves twoIntroduction About This ManualOverview Application and InstallationInstallation ApplicationLocation Installation OverviewCold Climates and Derating Factors Outdoor LocationsGenset Sizing „ Static Uninterrupted Power Supplies UPSGenset Sizing Procedure Generator Set Sizing CalculationsStep Sequence Guidelines 765.7 Repeat steps a and b as necessary through all the worksheets Running load should not be Generator Set Sizing Calculations Select a Generator SetEstablish the minimum size required Single-Phase Induction Motor Genset Sizing Determining Load CharacteristicsDetermining Load Characteristics Lighting Calculate SkVA as follows Genset Sizing Determining Load CharacteristicsThree-Phase Induction Motors Full SkVA Determining Load CharacteristicsCalculate SkW as follows 100Three Phase Nema Motor Code Table 201Static UPS Synchronous MotorsVariable Frequency Drives Equation above Output kVA is the nameplate kVA capacityNoise Laws and Regulations Noise ConsiderationRadiator discharge air high frequency sound Noise Zones Peak DayComparison Chart dBA Environmental Considerations dBAAdding Additional Sound Sources Below estimates the noise level from multiple noise sourcesEffects of Distance Distance Effects on dBASee on page 32 for typical measures in reducing noise Reducing NoiseFollowing will help reduce structure-borne noise Following will help reduce airborne noiseAcoustic Material Reducing NoiseMounting on a Slab Floor Access to SetMounting Mounting on a Sub-Base Fuel TankMounting Foundation Mounting FoundationVibration Isolators Mountingthe Generator SETGeneral Information Installation and Adjustment Procedure Mounting Vibration IsolatorsDiesel Fuel Mechanical Installation Fuel System DieselFuel System Installation Supply TankMechanical Installation Fuel System Diesel Diesel Fuel Supply Minimum Fuel Supply / Return Hose and Pipe SizesMechanical Installation Fuel System Gaseous Fuels Gaseous Fuel Supply Mechanical Installation Fuel System Gaseous FuelsContaminants Pipe and Tube Sizing Natural GAS Schedule 40 Iron Pipe SizingTypical Pipe Schematic for Propane Vapor Distribution Mechanical Installation Fuel System Liquid Propane Schedule 40 Iron Pipe SizingAdditional references include Fuel Storage RegulationsEnvironmental Protection Field Installing a Generator Exhaust System Mechanical Installation Exhaust SystemExhaust System Installation Mechanical Installation Exhaust System Condensation Trap Exhaust System Installation Reference Data Factory Recommended Engine Exhaust SilencersMQ Power Batteries Mechanical Installation Battery SystemPurpose of the Battery How BatteriesWorkEngine Starting System Mechanical Installation Battery System„ See the Battery Safety Instructions on Preparation of Charged and Wet Batteries Mechanical Installation NEW BatteryNew Battery Installation Preparation of Dry Charged Charged and Moist BatteriesDry Charged Batteries Mechanical Installation NEW BatteryRemoving Old Battery Charged and Moist Batteries ActivationStep One 1 -Visual Inspection See Flow Chart, on next Battery System -TESTING BatteryBatteryTesting Step Three 3 Load ProcedureBattery System Batterytesting Chart Battery Testing ChartCharging LowWater-loss Batteries Battery System Charging BatteryBattery Storage Battery System Battery Charger LC1224-500-2 Battery Charger Battery System Battery ChargerFC & FCA Battery Charger FC1224-10-2011U Battery ChargerBattery Charger Safety Battery System Battery Charger SafetyBattery Charger Installation Ventilation and Cooling Mechanical Installation -VENTILATION and CoolingEngine Cooling Vents and DuctsMechanical Installation -VENTILATION and Cooling LouversMechanical Installation Mounted Radiator Cooling Factory Mounted RadiatorVentilationRadiator Set Requirements Mechanical Installation Mounted Radiator CoolingMounted Radiator Cooling System Mechanical Installation Remote Radiator Cooling Remote Radiator Cooling optionalMechanical Installation Remote Radiator Cooling Remote Radiator CoolingMechanical Installation Hotwell Cooling Hot Well Installation19,200/60x8 = 40 gpm Mechanical Installation Heat Exchanger CoolingHeat Exchanger Coolant Heaters Coolant TreatmentCoolantTreatment Electrical Installation DC Controlwiring Control box contains the following „ Digital Control Module DC Control Wiring Control BOX Back PanelControl Box „ Control Box Back Panel ComponentsDC Controlwiring Control BOX Back Panel L3 3 PHGenerator Set Wire Diagram Transfer Switch AC Electrical ConnectionsAC Electrical Connections Connection Of Generator Leads For Correct Voltage OutputBreaker Electrical TerminationsMounted fuel tank is used, the electrical stub-up Line circuit breakerAC Electrical Connections System Grounding AC Electrical Connections System Grounding Pole ATSAC Electrical Connections Equipment Grounding Equipment GroundingElectrical Distribution System Electrical Distribution SystemPRE-START Preparation PRE-START Preparation Run the Generator SetAppendix Installation Checklist For MQ Power Industrial Generators Appendix MAIN-LINE Circuit BreakerAppendix MAIN-LINE Circuit Breaker Appendix Generator Specifications MQ Power Industrial Generator SpecificationsAppendix Generator Specifications MQ Power Industrial Generator Specifications Appendix Engine Specifications Appendix Engine Specifications MQP175IV MQP200IV MQP250IVGenerator Model MQP300IV MQP350IV MQP400IV Appendix Engine Specifications Generator Model MQP30GM MQP45GM MQP60GM MQP80GM MQP100GMAppendix Dimensions and Weights MQ Power Generator Dimensions & WeightsAppendix Dimensions Andweights MQ Power Generator Dimensions & WeightsHeres HOW to GET Help