Multiquip MQP30DZ Battery System -TESTING Battery, BatteryTesting, Step Three 3 Load Procedure

Page 54

BATTERY SYSTEM —TESTING BATTERY

BatteryTesting

Before conducting any battery tests, refer to page 11 for battery safety instructions.

Low water-loss batteries of the latest design may incorporate flame-arrester vents to reduce the possibility of explosions caused by external sparks. Therefore, during charging and testing, the flame-arrester vents should remain in place.

Refer to Figure 18, Battery Testing Chart on page 55.

Step One (1) -Visual Inspection (See Flow Chart, Figure 18 on next page)

a.Visually inspect the battery for container, cover, or terminal damage that may have caused leakage of electrolyte or internal damage. If damage is found, replace the battery.

b.Check the condition and the size of the battery cables. Check for corrosion on the battery terminals and cable terminations. Corrosion on side terminal batteries may not be evident until the cables have been removed. Replace badly corroded cables or cables with defective terminations. Make certain the ground cable is making a good connection where it is grounded. Check the connection of the cable to the starter relay or solenoid. Proceed to step two.

Step Two (2) - Electrolyte Levels and State of Charge

Although these batteries are designed to preclude adding water, the volume of reserve electrolyte above the plates may eventually be depleted. In most cases, this will signal the end of the battery's useful life. Since many have sealed covers in place of filler caps, it may not be possible to check the electrolyte levels by looking directly into the cells. However, many low water loss batteries are contained in translucent plastic cases which may allow electrolyte levels to be seen. Other models utilize built-in hydrometers which also serve as electrolyte level indicators. If electrolyte levels can be seen and found to be low, check for a charging system malfunction.

If the electrolyte level is below the top of the plates in any cell, and if vents are removable, add water before proceeding further. If water cannot be added, replace the battery.

The battery must be at an adequate state of charge in order for the following load test to be valid. If the battery does not contain a built-in hydrometer, the state-of charge can be estimated with an accurate voltmeter.

a.If the stabilized open circuit voltage is below 12.4 volts, charge the battery (or check battery charger connection). A stabilized voltage reading is assumed after the battery has remained on open circuit for a minimum of 4 hours or, preferably, overnight. When a hydrometer reading can be taken, a value of 1.225 @ 80°F (26.7°C) can be used instead of the 12.4 voltage reading. If the battery has a built-in hydrometer, follow the instructions of the manufacturer. After the battery is charged, proceed to step 2.c.

b.If the state-of-charge of a battery cannot be determined, it must be charged. After the battery is charge, proceed to step 2.c.

c.Remove surface charge by attaching load test leads to the terminals and applying a load equal to 1/2 of the cold cranking amps at 0°F (-17.8°C) rating of the battery for 15 seconds. Manufacturers may prescribe specific methods. Follow specific instructions when they are available. Proceed to step 3.

d.If the stabilized voltage of the battery was 12.4 or above when it was first examined, or the built-in hydrometer indicated the battery was charge, proceed to step 3.

Step Three (3) - Load Procedure

The load test is conducted to determine if the battery has adequate electrical performance or if it has to be replaced. This procedure is valid only if the battery is at or above the state of charge specified in step 2.

a.Connect the voltmeter and load test leads to the battery terminals; be sure the load switch is in the "Off" position Proceed to step 3.b.

b.Apply a load test equal to 1/2 of the cold cranking rating of the battery at 0°F (-17.8°C). Read voltage after fifteen (15) seconds with the load connected. Remove load. Estimate or measure the battery temperature and compare voltage reading with the voltage chart (see Figure 17 on page 53). If the voltage is less than the minimum specified, replace the battery. If the voltage meets or exceeds the specified minimum, return the battery to service.

PAGE 54 — INDUSTRIAL GENERATOR SETS — APPLICATION & INSTALLATION MANUAL — REV. #4 (09/07/07)

Image 54
Contents MQ Power Application & Installation ManualPage Heres HOW to GET Help Table of Contents Page Safety Message Alert Symbols Foryour Safety and the Safety of OthersSafety Message Alert Symbols Accidental StartingImportant Safety Instructions General SafetyImportant Safety Instructions General Safety RadiatorEmergencies Operation SafetyMaintenance Safety Always know the location of the nearest fire extinguisherBattery Safety Fire Protection Genset should be inspected regularly for fire hazardsLifting the Generator Set Always drain fuel prior to liftingIntroduction Always remember Safety FIRST!!! Safety involves twoIntroduction About This ManualOverview Application and InstallationInstallation ApplicationLocation Installation OverviewCold Climates and Derating Factors Outdoor LocationsGenset Sizing „ Static Uninterrupted Power Supplies UPSGenset Sizing Procedure Generator Set Sizing CalculationsStep Sequence Guidelines 765.7 Repeat steps a and b as necessary through all the worksheets Generator Set Sizing Calculations Select a Generator Set Establish the minimum size requiredRunning load should not be Genset Sizing Determining Load Characteristics Determining Load Characteristics LightingSingle-Phase Induction Motor Genset Sizing Determining Load Characteristics Three-Phase Induction MotorsCalculate SkVA as follows Full SkVA Determining Load CharacteristicsCalculate SkW as follows 100Three Phase Nema Motor Code Table 201Static UPS Synchronous MotorsVariable Frequency Drives Equation above Output kVA is the nameplate kVA capacityNoise Laws and Regulations Noise ConsiderationRadiator discharge air high frequency sound Noise Zones Peak DayComparison Chart dBA Environmental Considerations dBAAdding Additional Sound Sources Below estimates the noise level from multiple noise sourcesEffects of Distance Distance Effects on dBASee on page 32 for typical measures in reducing noise Reducing NoiseFollowing will help reduce structure-borne noise Following will help reduce airborne noiseAcoustic Material Reducing NoiseMounting on a Slab Floor Access to SetMounting Mounting on a Sub-Base Fuel TankMounting Foundation Mounting FoundationMountingthe Generator SET General InformationVibration Isolators Installation and Adjustment Procedure Mounting Vibration IsolatorsDiesel Fuel Mechanical Installation Fuel System DieselFuel System Installation Supply TankMechanical Installation Fuel System Diesel Diesel Fuel Supply Minimum Fuel Supply / Return Hose and Pipe SizesMechanical Installation Fuel System Gaseous Fuels Mechanical Installation Fuel System Gaseous Fuels ContaminantsGaseous Fuel Supply Pipe and Tube Sizing Natural GAS Schedule 40 Iron Pipe SizingTypical Pipe Schematic for Propane Vapor Distribution Mechanical Installation Fuel System Liquid Propane Schedule 40 Iron Pipe SizingFuel Storage Regulations Environmental ProtectionAdditional references include Mechanical Installation Exhaust System Exhaust System InstallationField Installing a Generator Exhaust System Mechanical Installation Exhaust System Condensation Trap Exhaust System Installation Reference Data Factory Recommended Engine Exhaust SilencersMQ Power Batteries Mechanical Installation Battery SystemPurpose of the Battery How BatteriesWorkMechanical Installation Battery System „ See the Battery Safety Instructions onEngine Starting System Preparation of Charged and Wet Batteries Mechanical Installation NEW BatteryNew Battery Installation Preparation of Dry Charged Charged and Moist BatteriesDry Charged Batteries Mechanical Installation NEW BatteryRemoving Old Battery Charged and Moist Batteries ActivationStep One 1 -Visual Inspection See Flow Chart, on next Battery System -TESTING BatteryBatteryTesting Step Three 3 Load ProcedureBattery System Batterytesting Chart Battery Testing ChartBattery System Charging Battery Battery StorageCharging LowWater-loss Batteries Battery System Battery Charger LC1224-500-2 Battery Charger Battery System Battery ChargerFC & FCA Battery Charger FC1224-10-2011U Battery ChargerBattery System Battery Charger Safety Battery Charger InstallationBattery Charger Safety Ventilation and Cooling Mechanical Installation -VENTILATION and CoolingEngine Cooling Vents and DuctsMechanical Installation -VENTILATION and Cooling LouversMechanical Installation Mounted Radiator Cooling Factory Mounted RadiatorVentilationMechanical Installation Mounted Radiator Cooling Mounted Radiator Cooling SystemRadiator Set Requirements Mechanical Installation Remote Radiator Cooling Remote Radiator Cooling optionalMechanical Installation Remote Radiator Cooling Remote Radiator CoolingMechanical Installation Hotwell Cooling Hot Well InstallationMechanical Installation Heat Exchanger Cooling Heat Exchanger19,200/60x8 = 40 gpm Coolant Treatment CoolantTreatmentCoolant Heaters Electrical Installation DC Controlwiring Control box contains the following „ Digital Control Module DC Control Wiring Control BOX Back PanelControl Box „ Control Box Back Panel ComponentsDC Controlwiring Control BOX Back Panel L3 3 PHGenerator Set Wire Diagram Transfer Switch AC Electrical ConnectionsAC Electrical Connections Connection Of Generator Leads For Correct Voltage OutputBreaker Electrical TerminationsMounted fuel tank is used, the electrical stub-up Line circuit breakerAC Electrical Connections System Grounding AC Electrical Connections System Grounding Pole ATSAC Electrical Connections Equipment Grounding Equipment GroundingElectrical Distribution System Electrical Distribution SystemPRE-START Preparation PRE-START Preparation Run the Generator SetAppendix Installation Checklist For MQ Power Industrial Generators Appendix MAIN-LINE Circuit BreakerAppendix MAIN-LINE Circuit Breaker Appendix Generator Specifications MQ Power Industrial Generator SpecificationsAppendix Generator Specifications MQ Power Industrial Generator Specifications Appendix Engine Specifications Appendix Engine Specifications MQP175IV MQP200IV MQP250IVGenerator Model MQP300IV MQP350IV MQP400IV Appendix Engine Specifications Generator Model MQP30GM MQP45GM MQP60GM MQP80GM MQP100GMAppendix Dimensions and Weights MQ Power Generator Dimensions & WeightsAppendix Dimensions Andweights MQ Power Generator Dimensions & WeightsHeres HOW to GET Help