Multiquip MQP60IV, MQP20IZ, MQP40IZ, MQP45GM Typical Pipe Schematic for Propane Vapor Distribution

Page 43

MECHANICAL INSTALLATION — FUEL SYSTEM (GASEOUS FUELS)

Figure 12. Typical Pipe Schematic for Propane Vapor Distribution

TABLE 14. PROPANE VAPOR SCHEDULE 40 IRON PIPE SIZING

Pipe Size (in.)

Length

1/2

3/4

 

1

1 1/4

1 1/2

2

3

 

3 1/2

4

(0.622)

(0.824)

 

(1.049)

(1.38)

(1.61)

(2.067)

(3.068)

 

(3.548)

(4.026)

(ft.)

 

 

 

 

Maximum capacity in thousands of BTU per hour

 

 

 

 

 

 

 

10

291

608

 

1145

2352

3523

6786

19119

 

27993

38997

 

 

 

 

 

 

 

 

 

 

 

 

20

200

418

 

787

1616

2422

4664

13141

 

19240

26802

30

160

336

 

632

1298

1945

3745

10552

 

15450

21523

 

 

 

 

 

 

 

 

 

 

 

 

40

137

287

 

541

1111

1664

3205

9031

 

13223

18421

50

122

255

 

480

984

1475

2841

8004

 

11720

16326

60

110

231

 

434

892

1337

2574

7253

 

10619

14793

 

 

 

 

 

 

 

 

 

 

 

 

80

94

197

 

372

763

1144

2203

6207

 

9088

12661

100

84

175

 

330

677

1014

1952

5501

 

8055

11221

 

 

 

 

 

 

 

 

 

 

 

 

125

74

155

 

292

600

899

1730

4876

 

7139

9945

150

67

140

 

265

543

814

1568

4418

 

6468

9011

 

 

 

 

 

 

 

 

 

 

 

 

200

58

120

 

227

465

697

1342

3781

 

5536

7712

250

51

107

 

201

412

618

1189

3351

 

4906

6835

300

46

97

 

182

373

560

1078

3036

 

4446

6193

 

 

 

 

 

 

 

 

 

 

 

 

350

42

89

 

167

344

515

991

2793

 

4090

5698

400

40

83

 

156

320

479

922

2599

 

3805

5301

 

 

 

 

 

 

 

 

 

 

 

 

TABLE 15. PROPANE VAPOR SEMI-RIGID COPPER TUBING SIZING

Tube Size

K&L

1/4

3/8

1/2

5/8

3/4

1

1 1/4

1 1/2

2

2 1/2

(in.)

ACR

3/8

1/2

5/8

3/4

7/8

1 1/8

1 3/8

1 5/8

2 1/8

2 5/8

 

Outside

0.375

0.500

0.625

0.750

0.875

1.125

1.375

1.625

2.125

2.625

Inside *

0.305

0.402

0.527

0.652

0.745

0.995

1.245

1.481

1.959

2.435

 

 

 

 

 

 

 

 

 

 

 

 

Length (ft)

 

Maximum Capacity in Cubic Feet of Gas per Hour

 

 

 

 

 

 

 

 

 

 

 

 

 

10

 

45

93

188

329

467

997

1795

2830

5895

10429

 

 

 

 

 

 

 

 

 

 

 

 

20

 

31

64

129

226

321

685

1234

1945

4051

7168

 

 

 

 

 

 

 

 

 

 

 

 

30

 

25

51

104

182

258

550

991

1562

3253

5756

 

 

 

 

 

 

 

 

 

 

 

 

40

 

21

44

89

155

220

471

848

1337

2784

4926

50

 

19

39

79

138

195

417

752

1185

2468

4366

 

 

 

 

 

 

 

 

 

 

 

 

60

 

17

35

71

125

177

378

681

1074

2236

3956

70

 

16

32

66

115

163

348

626

988

2057

3639

80

 

15

30

61

107

152

324

583

919

1914

3386

90

 

14

28

57

100

142

304

546

862

1796

3177

100

 

13

27

54

95

134

287

517

814

1696

3001

125

 

11

24

48

84

119

254

458

722

1503

2660

150

 

10

21

44

76

108

230

415

654

1362

2410

175

 

10

20

40

70

99

212

382

602

1253

2217

200

 

8.9

18

37

65

92

197

355

560

1166

2062

225

 

8.3

17

35

61

87

185

333

525

1094

1935

250

 

7.9

16

33

58

82

175

315

496

1033

1828

275

 

7.5

15

31

55

78

166

299

471

981

1736

300

 

7.1

15

30

52

74

158

285

449

936

1656

*Table capacities are based on Type K copper tubing inside diameter (shown), which has the smallest inside diameter of the copper tubing products.

INDUSTRIAL GENERATOR SETS — APPLICATION & INSTALLATION MANUAL — REV. #4 (09/07/07) — PAGE 43

Image 43
Contents Application & Installation Manual MQ PowerPage Heres HOW to GET Help Table of Contents Page Foryour Safety and the Safety of Others Safety Message Alert SymbolsAccidental Starting Safety Message Alert SymbolsGeneral Safety Important Safety InstructionsGeneral Safety Radiator Important Safety InstructionsAlways know the location of the nearest fire extinguisher Operation SafetyMaintenance Safety EmergenciesBattery Safety Genset should be inspected regularly for fire hazards Fire ProtectionAlways drain fuel prior to lifting Lifting the Generator SetAbout This Manual Always remember Safety FIRST!!! Safety involves twoIntroduction IntroductionApplication Application and InstallationInstallation OverviewOutdoor Locations Installation OverviewCold Climates and Derating Factors LocationGenerator Set Sizing Calculations „ Static Uninterrupted Power Supplies UPSGenset Sizing Procedure Genset SizingStep Sequence Guidelines 765.7 Repeat steps a and b as necessary through all the worksheets Establish the minimum size required Generator Set Sizing Calculations Select a Generator SetRunning load should not be Determining Load Characteristics Lighting Genset Sizing Determining Load CharacteristicsSingle-Phase Induction Motor Three-Phase Induction Motors Genset Sizing Determining Load CharacteristicsCalculate SkVA as follows 100 Determining Load CharacteristicsCalculate SkW as follows Full SkVA201 Three Phase Nema Motor Code TableEquation above Output kVA is the nameplate kVA capacity Synchronous MotorsVariable Frequency Drives Static UPSNoise Zones Peak Day Noise ConsiderationRadiator discharge air high frequency sound Noise Laws and RegulationsEnvironmental Considerations dBA Comparison Chart dBABelow estimates the noise level from multiple noise sources Adding Additional Sound SourcesDistance Effects on dBA Effects of DistanceFollowing will help reduce airborne noise Reducing NoiseFollowing will help reduce structure-borne noise See on page 32 for typical measures in reducing noiseReducing Noise Acoustic MaterialMounting on a Sub-Base Fuel Tank Access to SetMounting Mounting on a Slab FloorMounting Foundation Mounting FoundationGeneral Information Mountingthe Generator SETVibration Isolators Mounting Vibration Isolators Installation and Adjustment ProcedureSupply Tank Mechanical Installation Fuel System DieselFuel System Installation Diesel FuelMechanical Installation Fuel System Diesel Minimum Fuel Supply / Return Hose and Pipe Sizes Diesel Fuel SupplyMechanical Installation Fuel System Gaseous Fuels Contaminants Mechanical Installation Fuel System Gaseous FuelsGaseous Fuel Supply Natural GAS Schedule 40 Iron Pipe Sizing Pipe and Tube SizingTypical Pipe Schematic for Propane Vapor Distribution Liquid Propane Schedule 40 Iron Pipe Sizing Mechanical Installation Fuel SystemEnvironmental Protection Fuel Storage RegulationsAdditional references include Exhaust System Installation Mechanical Installation Exhaust SystemField Installing a Generator Exhaust System Mechanical Installation Exhaust System Condensation Trap Factory Recommended Engine Exhaust Silencers Exhaust System Installation Reference DataHow BatteriesWork Mechanical Installation Battery SystemPurpose of the Battery MQ Power Batteries„ See the Battery Safety Instructions on Mechanical Installation Battery SystemEngine Starting System Preparation of Dry Charged Charged and Moist Batteries Mechanical Installation NEW BatteryNew Battery Installation Preparation of Charged and Wet BatteriesCharged and Moist Batteries Activation Mechanical Installation NEW BatteryRemoving Old Battery Dry Charged BatteriesStep Three 3 Load Procedure Battery System -TESTING BatteryBatteryTesting Step One 1 -Visual Inspection See Flow Chart, on nextBattery Testing Chart Battery System Batterytesting ChartBattery Storage Battery System Charging BatteryCharging LowWater-loss Batteries Battery System Battery Charger FC1224-10-2011U Battery Charger Battery System Battery ChargerFC & FCA Battery Charger LC1224-500-2 Battery ChargerBattery Charger Installation Battery System Battery Charger SafetyBattery Charger Safety Vents and Ducts Mechanical Installation -VENTILATION and CoolingEngine Cooling Ventilation and CoolingLouvers Mechanical Installation -VENTILATION and CoolingFactory Mounted RadiatorVentilation Mechanical Installation Mounted Radiator CoolingMounted Radiator Cooling System Mechanical Installation Mounted Radiator CoolingRadiator Set Requirements Remote Radiator Cooling optional Mechanical Installation Remote Radiator CoolingRemote Radiator Cooling Mechanical Installation Remote Radiator CoolingHot Well Installation Mechanical Installation Hotwell CoolingHeat Exchanger Mechanical Installation Heat Exchanger Cooling19,200/60x8 = 40 gpm CoolantTreatment Coolant TreatmentCoolant Heaters Electrical Installation DC Controlwiring „ Control Box Back Panel Components DC Control Wiring Control BOX Back PanelControl Box Control box contains the following „ Digital Control ModuleL3 3 PH DC Controlwiring Control BOX Back PanelGenerator Set Wire Diagram AC Electrical Connections Transfer SwitchConnection Of Generator Leads For Correct Voltage Output AC Electrical ConnectionsLine circuit breaker Electrical TerminationsMounted fuel tank is used, the electrical stub-up BreakerAC Electrical Connections System Grounding Pole ATS AC Electrical Connections System GroundingEquipment Grounding AC Electrical Connections Equipment GroundingElectrical Distribution System Electrical Distribution SystemPRE-START Preparation Run the Generator Set PRE-START PreparationAppendix Installation Checklist Appendix MAIN-LINE Circuit Breaker For MQ Power Industrial GeneratorsAppendix MAIN-LINE Circuit Breaker MQ Power Industrial Generator Specifications Appendix Generator SpecificationsAppendix Generator Specifications MQ Power Industrial Generator Specifications Appendix Engine Specifications MQP175IV MQP200IV MQP250IV Appendix Engine SpecificationsGenerator Model MQP300IV MQP350IV MQP400IV Generator Model MQP30GM MQP45GM MQP60GM MQP80GM MQP100GM Appendix Engine SpecificationsMQ Power Generator Dimensions & Weights Appendix Dimensions and WeightsMQ Power Generator Dimensions & Weights Appendix Dimensions AndweightsHeres HOW to GET Help