Multiquip MQP60IV, MQP20IZ Battery System Battery Charger Safety, Battery Charger Installation

Page 59

BATTERY SYSTEM — BATTERY CHARGER SAFETY

Battery Charger Installation

All work should be completed by qualified persons familiar with the installation, construction and operation of generator sets. All work should be completed in accordance with the National Electric Code (NEC), Uniform Building Code (UBC) and other state or local codes.

If the battery charger installation is to be completed on-site, consider the following recommendations:

1.Select a suitable mounting location for the battery charger. If indoors, the charger can be installed in a NEMA 1 or NEMA 2 enclosure. If outdoors, the charger must be installed in a NEMA 3R, outdoor enclosure.

2.Mount the battery charger as close to the engine starting batteries as possible.

3.If the battery charger is to be generator set mounted, the charger should be shocked mounted to reduce engine vibration. Failure to do so could cause premature battery charger failure.

4.Verify the correct operational voltage for the charger and ensure the feeder providing power to the charger is protected by an appropriately sized, UL approved, circuit protection device.

5.All wiring and conduits should be sized and installed per NEC requirements.

6.AC voltage input terminations should match the voltage requirements of the battery charger. Ensure the DC output voltage of the charger matches the battery charging system of the engine-generator set.

7.Final DC wire terminations can be made by fitting the battery charger B+ (positive) to the B+ (positive) terminal on the engine electric starter mechanism. The battery charger ground (negative) should be fitted to the same lug where the engine starting battery ground cable is routed.

8.Secure all final battery charger connections (AC and DC) prior to energizing the circuit protection device feeding AC power to the charger.

9.Energize AC power and check the battery charger for proper operation.

Always be sure that the ground terminal provided on the battery charger is connected to a grounded wiring system.

Battery Charger Safety

The following safety precautions should always be used with MQ Power battery chargers.

zDO NOT operate if battery charger is dropped or otherwise damaged.

zDO NOT expose charger to rain or snow.

zDO NOT disassemble charger. Return to factory for service and repairs. Incorrect assembly may result in a risk of electric shock or fire.

zALWAYS de-energize and disconnect the AC input and the battery from the charger if contact with the battery charger is necessary. Failure to do so may result in electric shock.

zDuring normal operation, batteries may produce explosive hydrogen gas. NEVER smoke, use an open flame, or create sparks near the battery or charger.

Changing the factory-set potentiometer voids the warranty. Contact the factory if the setting on the charger is incorrect.

If the charger is not working correctly, first check the following:

1.Is AC power available to the charger?

2.Is the charger connected to a battery of the correct voltage? (The charger must be connected to a battery for it to operate at the correct voltage.)

3.Is the charger damaged? (Check for debris, particularly metal, inside the charger enclosure.)

4.If the charger appears not to be working check the battery's state of charge. If the battery is fully charged it is sometimes normal for the charger to indicate zero current flow. Also check the battery for shorted or open cells.

5.If the battery is being overcharged or undercharged, check whether the output voltage settings have been tampered with. The potentiometers should be covered with either white adhesive paper dots or a hard red varnish.

6.If charger is still not working properly, call the factory for assistance.

INDUSTRIAL GENERATOR SETS — APPLICATION & INSTALLATION MANUAL — REV. #4 (09/07/07) — PAGE 59

Image 59
Contents Application & Installation Manual MQ PowerPage Heres HOW to GET Help Table of Contents Page Foryour Safety and the Safety of Others Safety Message Alert SymbolsAccidental Starting Safety Message Alert SymbolsGeneral Safety Important Safety InstructionsGeneral Safety Radiator Important Safety InstructionsAlways know the location of the nearest fire extinguisher Operation SafetyMaintenance Safety EmergenciesBattery Safety Genset should be inspected regularly for fire hazards Fire ProtectionAlways drain fuel prior to lifting Lifting the Generator SetAbout This Manual Always remember Safety FIRST!!! Safety involves twoIntroduction IntroductionApplication Application and InstallationInstallation OverviewOutdoor Locations Installation OverviewCold Climates and Derating Factors LocationGenerator Set Sizing Calculations „ Static Uninterrupted Power Supplies UPSGenset Sizing Procedure Genset SizingStep Sequence Guidelines 765.7 Repeat steps a and b as necessary through all the worksheets Running load should not be Generator Set Sizing Calculations Select a Generator SetEstablish the minimum size required Single-Phase Induction Motor Genset Sizing Determining Load CharacteristicsDetermining Load Characteristics Lighting Calculate SkVA as follows Genset Sizing Determining Load CharacteristicsThree-Phase Induction Motors 100 Determining Load CharacteristicsCalculate SkW as follows Full SkVA201 Three Phase Nema Motor Code TableEquation above Output kVA is the nameplate kVA capacity Synchronous MotorsVariable Frequency Drives Static UPSNoise Zones Peak Day Noise ConsiderationRadiator discharge air high frequency sound Noise Laws and RegulationsEnvironmental Considerations dBA Comparison Chart dBABelow estimates the noise level from multiple noise sources Adding Additional Sound SourcesDistance Effects on dBA Effects of DistanceFollowing will help reduce airborne noise Reducing NoiseFollowing will help reduce structure-borne noise See on page 32 for typical measures in reducing noiseReducing Noise Acoustic MaterialMounting on a Sub-Base Fuel Tank Access to SetMounting Mounting on a Slab FloorMounting Foundation Mounting FoundationVibration Isolators Mountingthe Generator SETGeneral Information Mounting Vibration Isolators Installation and Adjustment ProcedureSupply Tank Mechanical Installation Fuel System DieselFuel System Installation Diesel FuelMechanical Installation Fuel System Diesel Minimum Fuel Supply / Return Hose and Pipe Sizes Diesel Fuel SupplyMechanical Installation Fuel System Gaseous Fuels Gaseous Fuel Supply Mechanical Installation Fuel System Gaseous FuelsContaminants Natural GAS Schedule 40 Iron Pipe Sizing Pipe and Tube SizingTypical Pipe Schematic for Propane Vapor Distribution Liquid Propane Schedule 40 Iron Pipe Sizing Mechanical Installation Fuel SystemAdditional references include Fuel Storage RegulationsEnvironmental Protection Field Installing a Generator Exhaust System Mechanical Installation Exhaust SystemExhaust System Installation Mechanical Installation Exhaust System Condensation Trap Factory Recommended Engine Exhaust Silencers Exhaust System Installation Reference DataHow BatteriesWork Mechanical Installation Battery SystemPurpose of the Battery MQ Power BatteriesEngine Starting System Mechanical Installation Battery System„ See the Battery Safety Instructions on Preparation of Dry Charged Charged and Moist Batteries Mechanical Installation NEW BatteryNew Battery Installation Preparation of Charged and Wet BatteriesCharged and Moist Batteries Activation Mechanical Installation NEW BatteryRemoving Old Battery Dry Charged BatteriesStep Three 3 Load Procedure Battery System -TESTING BatteryBatteryTesting Step One 1 -Visual Inspection See Flow Chart, on nextBattery Testing Chart Battery System Batterytesting ChartCharging LowWater-loss Batteries Battery System Charging BatteryBattery Storage Battery System Battery Charger FC1224-10-2011U Battery Charger Battery System Battery ChargerFC & FCA Battery Charger LC1224-500-2 Battery ChargerBattery Charger Safety Battery System Battery Charger SafetyBattery Charger Installation Vents and Ducts Mechanical Installation -VENTILATION and CoolingEngine Cooling Ventilation and CoolingLouvers Mechanical Installation -VENTILATION and CoolingFactory Mounted RadiatorVentilation Mechanical Installation Mounted Radiator CoolingRadiator Set Requirements Mechanical Installation Mounted Radiator CoolingMounted Radiator Cooling System Remote Radiator Cooling optional Mechanical Installation Remote Radiator CoolingRemote Radiator Cooling Mechanical Installation Remote Radiator CoolingHot Well Installation Mechanical Installation Hotwell Cooling19,200/60x8 = 40 gpm Mechanical Installation Heat Exchanger CoolingHeat Exchanger Coolant Heaters Coolant TreatmentCoolantTreatment Electrical Installation DC Controlwiring „ Control Box Back Panel Components DC Control Wiring Control BOX Back PanelControl Box Control box contains the following „ Digital Control ModuleL3 3 PH DC Controlwiring Control BOX Back PanelGenerator Set Wire Diagram AC Electrical Connections Transfer SwitchConnection Of Generator Leads For Correct Voltage Output AC Electrical ConnectionsLine circuit breaker Electrical TerminationsMounted fuel tank is used, the electrical stub-up BreakerAC Electrical Connections System Grounding Pole ATS AC Electrical Connections System GroundingEquipment Grounding AC Electrical Connections Equipment GroundingElectrical Distribution System Electrical Distribution SystemPRE-START Preparation Run the Generator Set PRE-START PreparationAppendix Installation Checklist Appendix MAIN-LINE Circuit Breaker For MQ Power Industrial GeneratorsAppendix MAIN-LINE Circuit Breaker MQ Power Industrial Generator Specifications Appendix Generator SpecificationsAppendix Generator Specifications MQ Power Industrial Generator Specifications Appendix Engine Specifications MQP175IV MQP200IV MQP250IV Appendix Engine SpecificationsGenerator Model MQP300IV MQP350IV MQP400IV Generator Model MQP30GM MQP45GM MQP60GM MQP80GM MQP100GM Appendix Engine SpecificationsMQ Power Generator Dimensions & Weights Appendix Dimensions and WeightsMQ Power Generator Dimensions & Weights Appendix Dimensions AndweightsHeres HOW to GET Help