Chapter 2 Installation

15

2.2Installation Procedures

2.2.1Cabinet Installation

Installation on the floor

Step 1: mark the position where the power system is to be installed.

Determine the installation position of the power supply cabinet in the power room according to the installation chart. Based on the mechanical specifications (see Fig. 2-1) of the installation holes of the power supply cabinet, determine the accurate position of the center points of the installation holes on the floor, and mark them with a pencil or oil pen.

(Applicable to the cabinet with 600mm depth)

(Applicable to the cabinet with 600mm depth)

Figure 2-1 Installation dimensions of the cabinet base

Step 2: drill reserve holes.

The expansive pipes delivered with the power system are M10%55mm, therefore, use electric drill with drill bit Φ12 and depth 70mm to drill holes at the center points of the installation holes marked on the ground. To avoid being off-center, be careful

ACTURA Flex 48330 Power System User Manual

Page 25
Image 25
Emerson 48330 user manual Installation Procedures, Cabinet Installation, Installation on the floor, Drill reserve holes