Vertical brace clamp assy.

Oxymitter 4000

Instruction Manual

IM-106-340, Rev. 4.0 May 2006

Figure 2-6. Oxymitter 4000 Abrasive Shield Bracing Installation

Brace Bars

(Not by Rosemount Analytical)

2.00

(51)

60o Max

1.00

(25)

Note: Dimensions are in inches with millimeters in parentheses.

Horizontal brace clamp assy. } By Rosemount Analytical (Both brace clamp assemblies are the same.

Installation and location of clamp assemblies and brace bars to be done in field.)

30o Min

4.12

(105)

4.12

(105)

2 Holes - 0.625

(16) Dia for

0.50 (12) Dia

Bolt5.62

(143)

0.375

(10)

5.62

(143)

1.00

(25) Max

Abrasive Shield

36.00 (914)

Note: Bracing is for vertical and horizontal Oxymitter 4000 Installation. External bracing required for 9 ft. through 18 ft. (2,75 m through 5,49 m) probes as shown above.

36920003

5.In vertical installations, ensure the system cable drops vertically from the Oxymitter 4000 and the conduit is routed below the level of the electronics housing. This drip loop minimizes the possibility that moisture will damage the electronics (Figure 2-8).

6.If the system has an abrasive shield, check the dust seal gaskets. The joints in the two gaskets must be staggered 180°. Also, make sure the gaskets are in the hub grooves as the Oxymitter 4000 slides into the 15° forcing cone in the abrasive shield.

7.Insert probe through the opening in the mounting flange and bolt the unit to the flange. When probe lengths selected are 9 to 18 ft (2.74 to

5.49 m), special brackets are supplied to provide additional support for the probe inside the flue or stack (Figure 2-6).

NOTE

If process temperatures will exceed 392°F (200°C), use anti-seize compound on stud threads to ease future removal of Oxymitter 4000. For ambient temperatures that will exceed 185°F (85°C), we recommend the remote mounted electronics option.

2-8

Page 46
Image 46
Emerson Process Management IM-106-340 instruction manual Oxymitter 4000 Abrasive Shield Bracing Installation