Chapter 3

Preparing the Site for Router Installation

This chapter describes how to prepare your site for installation of the MX240 router. It discusses the following topics:

Site Preparation Checklist on page 29

Cabinet Requirements on page 30

Rack Requirements on page 31

Clearance Requirements for Airflow and Hardware Maintenance on page 32

Site Preparation Checklist

The checklist in Table 19 on page 29 summarizes the tasks you must perform when preparing a site for router installation.

Table 19: Site Preparation Checklist

Item or Task

For More Information

Performed By

Date

Verify that environmental factors such as

“Router Environmental

 

 

temperature and humidity do not exceed router

Specifications” on page 163

 

 

tolerances.

 

 

 

Select the type of rack or cabinet.

“Cabinet Requirements” on page 30,

 

 

 

“Rack Requirements” on page 31

 

 

Plan rack or cabinet location, including required

“Cabinet Size and Clearance

 

 

space clearances.

Requirements” on page 30,

 

 

 

“Rack Size and Strength” on page 31,

 

 

 

“Clearance Requirements for Airflow

 

 

 

and Hardware

 

 

 

Maintenance” on page 32

 

 

If a rack is used, secure rack to floor and

“Connection to Building

 

 

building structure.

Structure” on page 32

 

 

Acquire cables and connectors.

 

 

 

Locate sites for connection of system

“Chassis Grounding

 

 

grounding.

Specifications” on page 165

 

 

Measure distance between external power

 

 

 

sources and router installation site.

 

 

 

Site Preparation Checklist 29