Preparing the Site for Router Installation
This chapter describes how to prepare your site for installation of the MX240 router. It discusses the following topics:
■Site Preparation Checklist on page 29
■Cabinet Requirements on page 30
■Rack Requirements on page 31
■Clearance Requirements for Airflow and Hardware Maintenance on page 32
Site Preparation Checklist
The checklist in Table 19 on page 29 summarizes the tasks you must perform when preparing a site for router installation.
Table 19: Site Preparation Checklist
Item or Task | For More Information | Performed By | Date |
Verify that environmental factors such as | “Router Environmental |
|
|
temperature and humidity do not exceed router | Specifications” on page 163 |
|
|
tolerances. |
|
|
|
Select the type of rack or cabinet. | “Cabinet Requirements” on page 30, |
|
|
| “Rack Requirements” on page 31 |
|
|
Plan rack or cabinet location, including required | “Cabinet Size and Clearance |
|
|
space clearances. | Requirements” on page 30, |
|
|
| “Rack Size and Strength” on page 31, |
|
|
| “Clearance Requirements for Airflow |
|
|
| and Hardware |
|
|
| Maintenance” on page 32 |
|
|
If a rack is used, secure rack to floor and | “Connection to Building |
|
|
building structure. | Structure” on page 32 |
|
|
Acquire cables and connectors. |
|
|
|
Locate sites for connection of system | “Chassis Grounding |
|
|
grounding. | Specifications” on page 165 |
|
|
Measure distance between external power |
|
|
|
sources and router installation site. |
|
|
|
Site Preparation Checklist ■ 29