Piping Schematics

Figure 67 Primary connection locations—downflow, air-Cooled, 28-42kW (8-12 ton) with scroll compressor models

Note: Drawing not to scale

Tolerance on all piping dimensions A is ± 1/2" (13mm)

 

 

 

All dimensions

 

 

 

 

 

 

 

 

 

 

 

 

from rear corner

 

 

 

 

A

of unit including

 

Front View

 

 

 

panels

 

Section A-A

 

 

 

X

O

 

 

 

 

 

 

 

 

Blower

16-1/16"

R

Outlet

(408mm)

 

 

4" (102mm) L1 L2 G1 G2

 

B

11-3/16"

ECS

(284mm)

 

HUM

LV1

CD

LV2

LV3

E1 E2 ECR

 

Front of Unit

Y

35"

(889mm)

 

 

 

 

73"

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(1854mm)

 

DPN000804

 

 

 

 

 

 

 

 

Rev. 2

 

 

 

 

 

 

 

 

 

 

 

 

 

X

 

Y

Connection Size / Opening

Point

Description

inches (mm)

 

inches (mm)

inches (mm)

R

Refrigerant Access

59-5/16 (1507)

 

 

14-3/4 (375)

11-3/16 x 4 (284 x 102)

 

 

 

 

 

 

 

 

 

 

L1

Liquid Line System 1

69-15/16 (1776)

 

16-13/16 (411)

1/2 Cu Sweat

 

 

 

 

 

 

 

 

 

 

L2

Liquid Line System 2

67-5/8 (1718)

 

 

16-13/16 (411)

1/2 Cu Sweat

 

 

 

 

 

 

 

 

 

 

G1

Hot Gas Discharge 1

65-1/2 (1664)

 

 

16-13/16 (411)

5/8 Cu Sweat

 

 

 

 

 

 

 

 

 

 

G2

Hot Gas Discharge 2

62-7/16 (1586)

 

 

16-13/16 (411)

5/8 Cu Sweat

 

 

 

 

 

 

 

 

 

 

CD

Condensate Drain*

46 (1168)

 

 

29-1/2 (749)

 

3/4 FPT

 

 

 

 

 

 

 

 

 

W/ Optional Pump

46 (1168)

 

 

29-1/2 (749)

1/2 Cu Sweat

 

 

 

 

 

 

 

 

 

 

 

 

 

HUM

Humidifier Supply Line

53-1/2 (1359)

 

 

29 (737)

1/4 Cu Sweat

 

 

 

 

 

 

 

 

 

 

ECS

Econ-O-Coil Supply

54-7/8 (1394)

 

 

22-9/16 (573)

1-5/8 Cu Sweat

 

 

 

 

 

 

 

 

 

 

ECR

Econ-O-Coil Return

49-3/8 (1254)

 

 

30-3/4 (781)

1-5/8 Cu Sweat

 

 

 

 

 

 

 

 

 

 

HS

Hot Water Reheat Supply

 

 

 

 

Consult factory

 

 

 

 

 

 

 

 

 

HR

Hot Water Reheat Return

 

 

 

 

Consult factory

 

 

 

 

 

 

 

 

 

 

E1

Electrical Connection (High Volt)

55-1/2 (1410)

 

 

31-1/4 (794)

2-1/2

 

 

 

 

 

 

 

 

 

 

E2

Electrical Connection (High Volt)

52-7/16 (1332)

 

 

31-1/4 (794)

2-1/2

 

 

 

 

 

 

 

 

 

 

LV1

Electrical Connection (Low Volt)

2-1/4 (57)

 

 

27 (686)

7/8

 

 

 

 

 

 

 

 

 

 

LV2

Electrical Connection (Low Volt)

2-1/4 (57)

 

 

29 (737)

7/8

 

 

 

 

 

 

 

 

 

 

LV3

Electrical Connection (Low Volt)

2-1/4 (57)

 

 

31 (787)

7/8

 

 

 

 

 

 

 

 

 

 

B

Blower Outlet

21-15/16 (557)

 

 

18-1/16 (459)

18-3/4 x 16-1/16 (476 x 408)

 

 

 

 

 

 

 

 

 

 

*Field-pitch condensate drain line a minimum of 1/8" (3.2mm) per foot (305mm). All units contain a factory-installed condensate trap. Do not trap external to the unit. Drain line may contain boiling water. Select appropriate drain system materials. The drain line must comply with all local codes.

92

Page 102
Image 102
Liebert DS user manual DPN000804