Liebert DS Piping Schematics, Front Section View, Connection Size / Opening, Point, Description

Models: DS

1 136
Download 136 pages 14.39 Kb
Page 113
Image 113
Front Section View

Piping Schematics

Figure 78 Primary connection locations—upflow, air-cooled, 53-77kW (15-22 ton), scroll compressor models

NOTE

1.Drawing not to scale.

2.Tolerance on all piping dimensions is ±1/2" (13mm).

3.Field-routed alternatives for refrigerant gas and liquid line connection points.

4.See submittal page DPN001191 for blower outlet and deck dimensional data.

 

 

 

All dimensions from

 

 

 

 

rear corner of unit

X

 

 

 

including panels

 

4"

Blower￿

Blower￿

 

 

Outlet

Outlet

 

(102mm)

 

35"

4" (102mm)

4

4

 

 

 

 

(889mm)

 

 

 

 

12-13/16"

 

 

Lv1

 

(325mm)

 

 

LV2

 

 

 

LV3

 

 

 

98"

 

 

 

 

(2489mm)

Front

Top View

O

Y

6"￿

(152mm)

17-3/16" (437mm)

CGD*

3-7/8"￿ 14-1/4"

(98mm) (362mm) 53kW (15 tons)/70 & 77kW (20 & 22 ton) 15-7/8" Manual background (403mm)

Left Side Section View

17-1/16" (433mm)

Factory Location

CGD*

Front Section View

DPN001213

(Left Front Panel Not Shown)

Rev. 1

 

 

X

 

Y

Connection Size / Opening

Point

Description

inches (mm)

inches (mm)

inches (mm)

 

 

 

 

 

R1 3

Refrigerant Access (Top)

83-5/8 (2124)

2 (51)

12 x 4 (305 x 102)

 

 

 

 

 

R2 3

Refrigerant Access (Bottom)

82-3/4 (2102)

14-3/4 (374)

12-3/16 x 4 (310 x 102)

 

 

 

 

 

 

 

 

 

 

 

53kW (15 tons)/70 & 77kW (20 & 22 ton)

 

 

 

 

 

L1

Liquid Line System 1

94-11/16 (2405)

16-3/4 (425)

1/2 / 5/8 Cu Sweat

 

 

 

 

 

L2

Liquid Line System 2

91-7/8 (2334)

16-3/4 (425)

1/2 / 5/8 Cu Sweat

 

 

 

 

 

G1

Hot Gas Discharge 1

88-3/4 (2254)

16-3/8 (416)

7/8 / 1-1/8 Cu Sweat

 

 

 

 

 

G2

Hot Gas Discharge 2

85-9/16 (2173)

16-3/8 (416)

7/8 / 1-1/8 Cu Sweat

 

 

 

 

 

 

R3 3

Refrigerant Access (Side)

-

 

-

6 x 17-3/16 (152 x 437)

 

 

 

 

 

 

CGD*

Condensate Gravity Drain

-

 

-

3/4 FPT

 

 

 

 

 

 

CPD

Condensate Pump Discharge (Opt)

79-5/16

(2015)

11-7/8 (302)

1/2 Cu Sweat

 

 

 

 

 

 

HUM

Humidifier Supply Line

79-5/16

(2015)

9-7/8 (251)

1/4 Cu Sweat

 

 

 

 

 

ECS**

Econ-O-Coil Supply

78-5/8 (1998)

7-7/8 (200)

2-1/8 Cu Sweat

 

 

 

 

 

ECR**

Econ-O-Coil Return

78-5/8 (1998)

4-5/8 (117)

2-1/8 Cu Sweat

 

 

 

 

 

E1

Electrical Connection (High Voltage)

75-3/8 (1915)

30 (762)

2-1/2

 

 

 

 

 

E2

Electrical Connection (High Voltage)

69-7/8 (1775)

30 (762)

2-1/2

 

 

 

 

 

 

LV1

Electrical Connection (Low Voltage)

19-1/2

(495)

29-1/16 (738)

7/8

 

 

 

 

 

 

LV2

Electrical Connection (Low Voltage)

19-1/2

(495)

30-1/2 (775)

7/8

 

 

 

 

 

 

LV3

Electrical Connection (Low Voltage)

19-1/2

(495)

31-15/16 (811)

7/8

 

 

 

 

 

 

*Field-pitch condensate drain line a minimum of 1/8" (3.2 mm) per foot (305 mm). All units contain a factory-installed condensate trap. Do not trap external to the unit. Drain line may contain boiling water. Select appropriate drain system materials. The drain line must comply with all local codes.

**Supplied on Dual-Cool systems only (4-pipe system)

103

Page 113
Image 113
Liebert DS user manual Piping Schematics, Front Section View, Connection Size / Opening, Point, Description, inches mm