Piping
8.0PIPING
All fluid and refrigeration connections to the unit, with the exception of the condensate drain, are sweat copper.
Refer to specific text and detailed diagrams in this manual for other
All piping below the elevated floor must be located so that it offers the least resistance to air flow. Careful planning of the piping layout under the raised floor is required to prevent the air flow from being blocked. When installing piping on the subfloor, it is recommended that the pipes be mounted in a horizontal plane rather than stacked one above the other. Whenever possible, the pipes should be run parallel to the air flow.
8.1Fluid Connections
NOTICE
This unit requires a water drain connection. It may require an external water supply to operate.
Improper installation, application and service practices can result in water leakage from the unit. Water leakage can cause severe property damage and loss of critical data center equipment.
Do not locate unit directly above any equipment that could sustain water damage. Emerson recommends installing leak detection equipment for unit and supply lines.
8.1.1Condensate Piping—Field-Installed
•Do not reduce drain lines
•Do not expose drain line to freezing temperatures
•Drain line may contain boiling water. Use copper or other suitable material
•Drain line must comply with local building codes
•Emerson recommends installing
Gravity Drain
•3/4" NPT drain connection is provided on units without optional
•Pitch drain line toward drain a minimum of 1/8" (3mm) per 1 foot (305mm) of length
•Drain is trapped internally. Do not trap external to equipment
•Drain line must be sized for 2 gpm (7.6 l/m) flow
NOTICE
The drain line must not be trapped outside the unit or water may back up in the drain pan.
72