Infrastructure

The onlyinfrastructure required for operating the transceiver and linking the sites is Power and Data/Signal connection to the peripheral networkingequipment.Thismustbereadypriortotheairlinkinstallation.

!IN OUTDOOR INSTALLATIONS, USE SHIELDED AND WEATHERPROOF MATERIALS (CABLES, INLETS, AND CONNECTORS) COMPLIANT TO THE SAFETY STANDARD IN FORCE.

Power

Source

The power requirement for standard units is 100-240VAC @ 50/60Hz - 10W.

Note: Units requiring low Voltage: 24-60 VDC - 10W can be factory set upon request.

It is recommended to use a Surge Suppression System to avoid damage to the equipment when power supply is unstable. Protection should be at least 25,000A.

Cabling

Standard 3-conductor power cords are required. (See Safety requirements, Page iv)

Data/Signal Cabling

1. ForTS700/155, TS700/G,TS800/155,TS800/155-F

Type

For connecting the Transceiver to the peripheral equipment, a dual- fiber cable is required (one fiber for transmission, the other for reception). The standard recommended cable is MM 62.5/125 µm fiber or SM 9/125 µm for fiber.

Connectors

Each fiber should be terminated with the ordered type of connector on the transceiver end (SC, ST).

Optical Fiber testing.

The cabling installer must specify the attenuation of each fiber installed.