4 – Installation

 

 

Installing a Switch

 

 

 

 

Installing a SANbox2-8c switch involves the following steps:

1.Mount the switch.

2.Install SFP transceivers.

3.Connect the management workstation to the switch.

4.Configure the management workstation.

5.Install the management application.

6.Start the management application.

7.Connect the switch to the AC power source.

8.Configure the switch.

9.Cable devices to the switch.

4.2.1

Mount the Switch

The switch can be placed on a flat surface and stacked or mounted in a 19” EIA rack. Refer to “Dimensions” on page A-3for weight and dimensional specifications. The top of each chassis has dimples to receive the rubber feet of a second chassis stacked on top. Without the rubber feet, the switch occupies 1U of space in an EIA rack. Mounting rails are required for rack installation and are available through QLogic Corporation.

WARNING!! Mount switches in the rack so that the weight is distributed evenly. An unevenly loaded rack can become unstable possibly resulting in equipment damage or personal injury.

AVERTISSEMENT!!

Installer les commutateurs dans l’armoire informatique de sorte que le poids soit réparti uniformément. Une armoire informatique déséquilibré risque d'entraîner des blessures ou d'endommager l'équipement.

WARNUNG!!

Switches so in das Rack einbauen, dass das Gewicht gleichmäßig verteilt ist. Ein Rack mit ungleichmäßiger Gewichtsverteilung kann schwanken/umfallen und Gerätbeschädigung oder Verletzung verursachen.