Baldor GLC80, GLC35, GLC50 Transfer Switch Transfer Switch Checklist, Transfer Switch Location

Page 29

Transfer Switch

Transfer Switch Checklist

A.Locate transfer switch in a clean, dry place, near the emergency load.

B.Provide a circuit breaker between the genset and the transfer switch.

C.Put a flexible connection between the conduit and genset.

D.Observe applicable codes in wiring–in the transfer switch and genset.

The transfer switch connects the genset to the emergency power system. The emergency power system may include several gensets and several transfer switches. Typically, the genset is wired to the emergency power system through a transfer switch as shown in Figure 2-17.

Figure 2-17 Typical Emergency power System Installations

Multiple Gensets can be arranged either in parallel or separately connected to dedicated emergency loads. Figure 2-17 also shows a typical arrangement of two gensets in parallel with transfer switches for loads that have different levels of priority. A typical multiple genset installation is shown for NFPA 110 Level 1 and Level 2 emergency power circuits and a priority control to select the appropriate transfer switch.

Wattmeters should be installed on each genset so load sharing can be checked. The control system should include an automatic paralleling control. Paralleling identical gensets is not difficult, but paralleling dissimilar sets can cause load sharing problems. When designing an installation that includes the paralleling of dissimilar generators, contract your nearby Baldor Distributor.

Transfer Switch Location

The transfer switch location is important and key considerations are:

1.Locate the transfer switch as close to the emergency load as practical to avoid interruptions of the emergency power system due to natural or man–made disasters, or to equipment failures. Consider several small transfer switches instead of one large one to increase reliability.

2.Locate the transfer switch in a clean, dry, well ventilated location, away from excessive heat. When the ambient air is above 104 °F (40 °C), fuses and circuit breakers must be derated. Allow adequate working space around the transfer switch.

3.A circuit breaker (or fuses) should be installed in the line between the generator and the transfer switch. Baldor Gensets are available with properly sized circuit breaker built into the generator control through 1200 amp breakers. The circuit breaker can be separately mounted. In the case of very large circuit breakers, a separate floor mounted circuit breaker is easier to wire up than a wall mounted breaker.

4.Install power and control wires in separate solid conduit with flexible sections at the genset. The flexible sections prevent vibration from damaging the conduit. All power conduits from the genset must contain all three phases.

5.Never install control wires in the same conduit as power conductors.

MN2408

General Information 2-19

Image 29
Contents GLC Generator California Proposition 65 Warning Table of Contents Appendix a Generator AC Metering Engine Parameter DisplayRead This Manual Thoroughly Section Product Safety InformationOperation SymbolsOperation Warning Statements Burn Installation Maintenance Product Safety Information MN2408 Labor Parts Limited WarrantyWarranty Period General Information MN2408 Site Planning Installation GuidelinesEngine Cooling System Controls and Transfer SwitchExhaust System Room AirVibration Isolators Foundation Design Foundation ChecklistSetting The Genset On An Existing Concrete Floor Slab Approximate Weight vs. kW Output Weight Of The GensetCalculate Soil Bearing Load SBL Capacity Designing An Isolated FoundationApproximate Load Bearing Capacities of Various Soil Types Typical Foundation InstallationSystem Placement Exhaust System Exhaust ChecklistMulti-Engine Installations Level Of AttenuationExhaust System Calculations Exhaust Piping Radiator Cooling Cooling System Cooling System ChecklistCooling System Design Engine Mounted Radiator Cooling Heat ExchangerCooling System Determination Remote Radiator Cooling Hot Well Installations11 Valves & Fittings and Fluid Flow in Pipe Other Considerations 13 Coolant Mixture Wind Barrier Air System Air System ChecklistEngine Crankcase Ventilation Transfer Switch Location Transfer Switch Transfer Switch ChecklistBattery Location Battery Starting SystemBattery Cables Battery ChargerGeneral Information MN2408 Generator Lifting When the Generator is installed outdoorsGenerator Mounting Mounting DimensionsVentilation Test Secure the GeneratorGuidelines for Exhaust System Hot Exhaust GassesBackpressure must not exceed 20 of water column Page General Considerations Fuel ConnectionsFuel Consumption Natural and LPG Natural Gas Flow Rate Cubic Feet per Hour per Pipe Length Example Determining Pipe Size for Natural GasNatural Gas Connections LP Gas Flow Rate Cubic Feet per Hour per Pipe Length Example Determining Pipe Size for LPGRating Transfer Switch ConsiderationsThree Phase WYE and Delta Connections Frame Ground Connection Battery Charger ConsiderationsGeneral Wiring Considerations Page Post Installation Checks Recommended Engine Oil and Battery TypeGLC100 GLC125Post Installation Checks On when the OFF Switch is used to stop the engine Run SwitchOperator Control Panel Digital Engine Controller Only Programming KeysAutomatic Start/Stop Operator Control PanelManual Start/Stop Automatic Mains Failure AMF Automatic Fault ShutdownUtility Power Restored Utility Power Failure ConditionsUtility Normal Condition Load Test Push-button OperationNo Load Test Engine Controller Inputs & Outputs Analog Faults Such as Fuel Rack Solenoids or electronic governors RunCrank Engine starter motorAction Description Display Comments Are no active faultsFront panel keypad push-button NormalOther time delay functions are Generator KVA Display Phase system not applicableVab Displays the generators output voltage Vbc Displays the generators output voltageBattery Voltage/Engine Speed Navigation Hints Main Menu Loop Voltage Calibration Procedure Displayed values Repeat for each phaseSpan Calibration Displays the type of calibration function Engine Temperature & Oil Pressure CalibrationOil Pressure UsedConfiguration Data Sheet Main Menu Loop Parameters 198 F Alarm Fault Name Input AnalogParameter Setting Volts A-B Battery VoltageEngine Control Connections 10 Analog Operator Control Panel Operator Control Panel Analog Engine Controller Only11 9957N Analog Engine Controller Connections 12 A121H Analog Engine Controller Connections Garretson Model KN Fuel Valve Considerations General ServiceInstallation Engine Section Troubleshooting and MaintenanceGeneral Troubleshooting Guide Problems and SolutionsTroubleshooting Guide Digital Controller Only Speed Troubleshooting Guide Analog Controller OnlyVerify the adjustments. Replace controller if failed DIODE, 1N5408 Part numberLAMP, #67, 12 Volt Replacement PartsGLC GLC125 Cable Jam Nut Flywheel Housing Magnetic PickupFLA GLC Circuit Breaker & Electrical DataGLC Data 259 300 MN2408 Series GLC A-7 144 150 GLC Wire Size Figure A-2 Customer Interface Connection Diagram MN2408 Series GLC A-11 Figure A-4 Single Phase w/o Breaker Connection Diagram Figure A-5 Single Phase One Breaker Connection Diagram Figure A-6 Single Phase Two Breaker Connection Diagram MN2408 Series GLC A-15 Series GLC MN2408 MN2408 Series GLC A-17 Series GLC MN2408 Figure A-11 Three Phase Connection Diagram Figure A-12 Three Phase Connection Diagram with PMG MN2408 Series GLC A-21 Series GLC MN2408 MN2408 Series GLC A-23 Series GLC MN2408 MN2408 Series GLC A-25 Series GLC MN2408 MN2408 Series GLC A-27 Figure A-20 Control Box Connections with MEC2 Controller Figure A-21 Engine Wiring, Woodward 4.3L GM Figure A-22 Engine Wiring, Woodward 5.7L GM Figure A-23 Engine Wiring, Woodward 8.1L GM Series GLC MN2408 Name Address Phone Model Number Job Number PowerStandby Continuous No LoadSwitch Adjust the AC voltage to match the normal sourceAre legible Proper belt alignment and tensionsBaldor District Offices Baldor Electric Company MN2408 04 FAR200