Baldor GLC125, GLC35, GLC80 Example Determining Pipe Size for Natural Gas, Natural Gas Connections

Page 39

Example: Determining Pipe Size for Natural Gas

A generator has a 16Hp engine 60 feet from the supply. Determine the supply pipe size for Natural Gas fuel.

16 x 10,000 = 160,000 BTU’s / per hour for proper operation.

160, 000 + 146 cubic feet per hour. 1, 096

From Table 3-6, a 60 foot run requires a minimum 1” pipe at full engine load.

Natural Gas Connections

The incoming pressure must be 11 inches water column (6 oz. pressure).

Table 3-5 Natural Gas Flow Rate (Cubic Feet per Hour) per Pipe Length

Pipe

 

 

 

 

 

Iron Pipe Size

 

 

 

 

 

Length

 

 

 

 

 

 

 

 

 

 

 

 

 

1/2

3/4

1

1–1/4

1–1/2

 

2

 

2–1/2

3

4

6

8

(Feet)

 

 

15

73

165

332

722

1174

 

2386

 

3704

6253

13352

37229

 

30

50

115

232

515

818

 

1712

 

2646

4521

9331

26330

53728

45

41

95

191

418

673

 

1419

 

2213

3752

7600

22462

43867

60

37

83

166

366

587

 

1241

 

1924

3319

6542

18595

37999

75

 

74

149

332

524

 

1077

 

1684

2886

5772

16652

33959

90

 

67

137

298

433

 

962

 

1501

2597

5291

15200

31025

105

 

63

126

274

 

 

885

 

1376

2357

4906

14064

28715

120

 

 

115

260

404

 

827

 

1289

2213

4618

13160

26859

150

 

 

105

233

366

 

750

 

1174

2011

4185

11775

24050

180

 

 

96

216

337

 

693

 

1077

1876

3848

10736

21934

210

 

 

89

197

308

 

635

 

991

1712

3559

9937

20298

240

 

 

 

183

289

 

596

 

933

1616

3357

9235

18990

270

 

 

 

171

274

 

558

 

875

1520

3127

8658

17903

300

 

 

 

164

260

 

524

 

827

1433

2886

8177

16998

Note: Almost all operation problems are related to the installation techniques used. Do Not guess, be sure pipe size is adequate for required flow rate.

1.Connect the proper size gas pipe at the Inlet Connection to the Fuel Lock Solenoid. Connect the Natural Gas pipe line shown in Figure 3-3 using the correct size pipe for the required flow rate and length of pipe. Refer to Table 3-5 for pipe size. Be certain that all connections are sealed and no leaks are present. The installer must ensure that all gas connections comply with all building codes.

2.Verify Fuel Supply Pressure

Prior to initial operation of generator, verify that fuel system pressure is 11Water Column (6 oz. pressure) and fuel pipe sizes comply with Table 3-5.

3.Proceed to Electrical Connections.

Figure 3-3 Gas Line Connections

Air Cleaner

Carburetor

Solenoid, Fuel Lock

Inlet Connection

Mounting Bracket

External Supply Piping (by installer)

U.L. requires a second shutoff valve and regulator to be installed in the supply piping to control the gas supply to the generator.

To Inlet

Supply Piping

 

Connection

 

Additional Regulator

Additional Valve

(11 - 14" water column pressure)

(Safety Shutoff Valve)

MN2408

Receiving & Installation 3-7

Image 39
Contents GLC Generator California Proposition 65 Warning Table of Contents Appendix a Generator AC Metering Engine Parameter DisplayRead This Manual Thoroughly Section Product Safety InformationOperation SymbolsOperation Warning Statements Burn Installation Maintenance Product Safety Information MN2408 Limited Warranty Warranty PeriodLabor Parts General Information MN2408 Site Planning Installation GuidelinesRoom Air Controls and Transfer SwitchEngine Cooling System Exhaust SystemFoundation Design Foundation Checklist Setting The Genset On An Existing Concrete Floor SlabVibration Isolators Approximate Weight vs. kW Output Weight Of The GensetCalculate Soil Bearing Load SBL Capacity Designing An Isolated FoundationApproximate Load Bearing Capacities of Various Soil Types Typical Foundation InstallationLevel Of Attenuation Exhaust System Exhaust ChecklistSystem Placement Multi-Engine InstallationsExhaust System Calculations Exhaust Piping Radiator Cooling Cooling System Cooling System ChecklistHeat Exchanger Cooling System DeterminationCooling System Design Engine Mounted Radiator Cooling Remote Radiator Cooling Hot Well Installations11 Valves & Fittings and Fluid Flow in Pipe Other Considerations 13 Coolant Mixture Wind Barrier Air System Air System ChecklistEngine Crankcase Ventilation Transfer Switch Location Transfer Switch Transfer Switch ChecklistBattery Location Battery Starting SystemBattery Cables Battery ChargerGeneral Information MN2408 Generator Lifting When the Generator is installed outdoorsGenerator Mounting Mounting DimensionsVentilation Test Secure the Generator Hot Exhaust Gasses Backpressure must not exceed 20 of water column Guidelines for Exhaust System Page Fuel Connections Fuel Consumption Natural and LPGGeneral Considerations Example Determining Pipe Size for Natural Gas Natural Gas ConnectionsNatural Gas Flow Rate Cubic Feet per Hour per Pipe Length LP Gas Flow Rate Cubic Feet per Hour per Pipe Length Example Determining Pipe Size for LPGRating Transfer Switch ConsiderationsThree Phase WYE and Delta Connections Battery Charger Considerations General Wiring ConsiderationsFrame Ground Connection Page GLC125 Recommended Engine Oil and Battery TypePost Installation Checks GLC100Post Installation Checks Programming Keys Run SwitchOn when the OFF Switch is used to stop the engine Operator Control Panel Digital Engine Controller OnlyOperator Control Panel Manual Start/StopAutomatic Start/Stop Automatic Mains Failure AMF Automatic Fault ShutdownLoad Test Push-button Operation Utility Power Failure ConditionsUtility Power Restored Utility Normal ConditionNo Load Test Engine Controller Inputs & Outputs Analog Faults Engine starter motor RunSuch as Fuel Rack Solenoids or electronic governors CrankNormal Are no active faultsAction Description Display Comments Front panel keypad push-buttonOther time delay functions are Vbc Displays the generators output voltage Phase system not applicableGenerator KVA Display Vab Displays the generators output voltageBattery Voltage/Engine Speed Navigation Hints Main Menu Loop Voltage Calibration Procedure Repeat for each phase Span CalibrationDisplayed values Used Engine Temperature & Oil Pressure CalibrationDisplays the type of calibration function Oil PressureConfiguration Data Sheet Main Menu Loop Parameters Battery Voltage Fault Name Input Analog198 F Alarm Parameter Setting Volts A-BEngine Control Connections 10 Analog Operator Control Panel Operator Control Panel Analog Engine Controller Only11 9957N Analog Engine Controller Connections 12 A121H Analog Engine Controller Connections Garretson Model KN Fuel Valve Considerations General ServiceInstallation Engine Section Troubleshooting and MaintenanceGeneral Troubleshooting Guide Problems and SolutionsTroubleshooting Guide Digital Controller Only Troubleshooting Guide Analog Controller Only Verify the adjustments. Replace controller if failedSpeed DIODE, 1N5408 Part numberReplacement Parts GLC GLC125LAMP, #67, 12 Volt Cable Jam Nut Flywheel Housing Magnetic PickupFLA GLC Circuit Breaker & Electrical DataGLC Data 259 300 MN2408 Series GLC A-7 144 150 GLC Wire Size Figure A-2 Customer Interface Connection Diagram MN2408 Series GLC A-11 Figure A-4 Single Phase w/o Breaker Connection Diagram Figure A-5 Single Phase One Breaker Connection Diagram Figure A-6 Single Phase Two Breaker Connection Diagram MN2408 Series GLC A-15 Series GLC MN2408 MN2408 Series GLC A-17 Series GLC MN2408 Figure A-11 Three Phase Connection Diagram Figure A-12 Three Phase Connection Diagram with PMG MN2408 Series GLC A-21 Series GLC MN2408 MN2408 Series GLC A-23 Series GLC MN2408 MN2408 Series GLC A-25 Series GLC MN2408 MN2408 Series GLC A-27 Figure A-20 Control Box Connections with MEC2 Controller Figure A-21 Engine Wiring, Woodward 4.3L GM Figure A-22 Engine Wiring, Woodward 5.7L GM Figure A-23 Engine Wiring, Woodward 8.1L GM Series GLC MN2408 No Load PowerName Address Phone Model Number Job Number Standby ContinuousProper belt alignment and tensions Adjust the AC voltage to match the normal sourceSwitch Are legibleBaldor District Offices Baldor Electric Company MN2408 04 FAR200