Baldor GLC80, GLC35, GLC50, GLC125 manual Generator Lifting, When the Generator is installed outdoors

Page 33

Section 3

Receiving & Installation

Receiving & Inspection When you receive your generator, there are several things you should do immediately.

1.Observe the condition of the shipping container and report any damage immediately to the commercial carrier that delivered your system.

2.Verify that the part number of the system you received is the same as the part number listed on your purchase order.

3.If the system is to be stored for several weeks before use, be sure that it is stored in a location that conforms to published storage temperature and humidity specifications.

Lifting the Generator When lift or hoist equipment is used to lift the generator and move it to position, be careful not to contact overhead wires or other obstacles. The generator can weigh as much as 3,000 lbs. Be sure lift or hoist equipment has appropriate tires for the terrain to avoid becoming stuck or tipping over. If the shipping pallet is intact, use a fork lift to move the generator. If the shipping pallet has been removed, use two steel pipes through the “Lift Point” holes to lift the generator. See Figure 3-1.

Figure 3-1 Generator Lifting

Height

To lift the generator, always use spreader bars, chains eyehooks and other hardware that is of sufficient strength to lift at least three times the weight of the generator.

Lift

Point

Length

Width

Lift Point

Physical Location The mounting location of the system is important. It should be installed in an area that is protected from direct harmful gases or liquids, dust, metallic particles, shock and vibration.

It should be installed in an outdoor location so the exhaust fumes are vented to the atmosphere.

When the Generator is installed outdoors

If the generator is installed outdoors there should not be a cooling problem. The factory installed enclosure is designed to keep out undesirable weather elements while providing cooling and ventilation.

When the Generator is installed in a building it is essential to provide:

1.Adequate control and exhausting of the heated air.

2.An adequate and constant supply of incoming cooling air.

3.Adequate control and discharge of the engine’s hot exhaust gases.

4.Adequate ventilation of the building when the engine shuts down.

MN2408

Receiving & Installation 3-1

Image 33
Contents GLC Generator California Proposition 65 Warning Table of Contents Appendix a Generator AC Metering Engine Parameter DisplayRead This Manual Thoroughly Section Product Safety InformationOperation SymbolsOperation Warning Statements Burn Installation Maintenance Product Safety Information MN2408 Limited Warranty Warranty PeriodLabor Parts General Information MN2408 Site Planning Installation GuidelinesEngine Cooling System Controls and Transfer SwitchExhaust System Room AirFoundation Design Foundation Checklist Setting The Genset On An Existing Concrete Floor SlabVibration Isolators Approximate Weight vs. kW Output Weight Of The GensetCalculate Soil Bearing Load SBL Capacity Designing An Isolated FoundationApproximate Load Bearing Capacities of Various Soil Types Typical Foundation InstallationSystem Placement Exhaust System Exhaust ChecklistMulti-Engine Installations Level Of AttenuationExhaust System Calculations Exhaust Piping Radiator Cooling Cooling System Cooling System ChecklistHeat Exchanger Cooling System DeterminationCooling System Design Engine Mounted Radiator Cooling Remote Radiator Cooling Hot Well Installations11 Valves & Fittings and Fluid Flow in Pipe Other Considerations 13 Coolant Mixture Wind Barrier Air System Air System ChecklistEngine Crankcase Ventilation Transfer Switch Location Transfer Switch Transfer Switch Checklist Battery Location Battery Starting SystemBattery Cables Battery ChargerGeneral Information MN2408 Generator Lifting When the Generator is installed outdoorsGenerator Mounting Mounting DimensionsVentilation Test Secure the GeneratorHot Exhaust Gasses Backpressure must not exceed 20 of water columnGuidelines for Exhaust System Page Fuel Connections Fuel Consumption Natural and LPGGeneral Considerations Example Determining Pipe Size for Natural Gas Natural Gas ConnectionsNatural Gas Flow Rate Cubic Feet per Hour per Pipe Length LP Gas Flow Rate Cubic Feet per Hour per Pipe Length Example Determining Pipe Size for LPGRating Transfer Switch ConsiderationsThree Phase WYE and Delta Connections Battery Charger Considerations General Wiring ConsiderationsFrame Ground Connection Page Post Installation Checks Recommended Engine Oil and Battery TypeGLC100 GLC125Post Installation Checks On when the OFF Switch is used to stop the engine Run SwitchOperator Control Panel Digital Engine Controller Only Programming KeysOperator Control Panel Manual Start/StopAutomatic Start/Stop Automatic Mains Failure AMF Automatic Fault ShutdownUtility Power Restored Utility Power Failure ConditionsUtility Normal Condition Load Test Push-button OperationNo Load Test Engine Controller Inputs & Outputs Analog Faults Such as Fuel Rack Solenoids or electronic governors RunCrank Engine starter motorAction Description Display Comments Are no active faultsFront panel keypad push-button NormalOther time delay functions are Generator KVA Display Phase system not applicableVab Displays the generators output voltage Vbc Displays the generators output voltageBattery Voltage/Engine Speed Navigation Hints Main Menu Loop Voltage Calibration Procedure Repeat for each phase Span CalibrationDisplayed values Displays the type of calibration function Engine Temperature & Oil Pressure CalibrationOil Pressure UsedConfiguration Data Sheet Main Menu Loop Parameters 198 F Alarm Fault Name Input AnalogParameter Setting Volts A-B Battery VoltageEngine Control Connections 10 Analog Operator Control Panel Operator Control Panel Analog Engine Controller Only11 9957N Analog Engine Controller Connections 12 A121H Analog Engine Controller Connections Garretson Model KN Fuel Valve Considerations General ServiceInstallation Engine Section Troubleshooting and MaintenanceGeneral Troubleshooting Guide Problems and SolutionsTroubleshooting Guide Digital Controller Only Troubleshooting Guide Analog Controller Only Verify the adjustments. Replace controller if failedSpeed DIODE, 1N5408 Part numberReplacement Parts GLC GLC125LAMP, #67, 12 Volt Cable Jam Nut Flywheel Housing Magnetic PickupFLA GLC Circuit Breaker & Electrical DataGLC Data 259 300 MN2408 Series GLC A-7 144 150 GLC Wire Size Figure A-2 Customer Interface Connection Diagram MN2408 Series GLC A-11 Figure A-4 Single Phase w/o Breaker Connection Diagram Figure A-5 Single Phase One Breaker Connection Diagram Figure A-6 Single Phase Two Breaker Connection Diagram MN2408 Series GLC A-15 Series GLC MN2408 MN2408 Series GLC A-17 Series GLC MN2408 Figure A-11 Three Phase Connection Diagram Figure A-12 Three Phase Connection Diagram with PMG MN2408 Series GLC A-21 Series GLC MN2408 MN2408 Series GLC A-23 Series GLC MN2408 MN2408 Series GLC A-25 Series GLC MN2408 MN2408 Series GLC A-27 Figure A-20 Control Box Connections with MEC2 Controller Figure A-21 Engine Wiring, Woodward 4.3L GM Figure A-22 Engine Wiring, Woodward 5.7L GM Figure A-23 Engine Wiring, Woodward 8.1L GM Series GLC MN2408 Name Address Phone Model Number Job Number PowerStandby Continuous No LoadSwitch Adjust the AC voltage to match the normal sourceAre legible Proper belt alignment and tensionsBaldor District Offices Baldor Electric Company MN2408 04 FAR200