Baldor GLC50, GLC35 Fuel Connections, Fuel Consumption Natural and LPG, General Considerations

Page 38

Installation

The generator is completely assembled, tested and adjusted at the factory before it is shipped to

 

you. The procedures presented in this manual are suggestions and it is the responsibility of the

 

Owner/Operator to arrange for these procedures to be performed by licensed contractors

 

according to all applicable codes including local codes for your Municipality/City/County and

 

State. External connections required at the time of installation are:

1. Fuel System.

2. Electrical Connections – power wiring (optional transfer switch) and control wiring.

3. Battery (not included).

4. Ground Connection.

After installation, the post installation checks must be performed prior to starting the engine.

After these checks have been performed and the system operation is verified to be good, refer to Section 5 Maintenance for periodic checks that must be performed at scheduled intervals to ensure continued operation with minimal problems.

Fuel Connections

Fuel selection is Natural Gas or LPG (Liquid Propane Gas). If natural gas supply is used, follow the “Natural Gas Connections” procedure. If LPG supply is used, follow the “LP Gas Connections” procedure. Table 3-4 defines the flow rate required for each fuel type.

Table 3-4 Fuel Consumption Natural and LPG

Generator Model

Fuel Consumption at 100% load (cubic feet per hour)

 

Natural Gas

LP Gas

GLC30

14.9

5.6

GLC35

16.3

6.0

GLC45

16.5

6.9

GLC50

20.7

8.2

GLC60

22.1

9.1

GLC80

28.7

12

GLC100

32.1

13.8

GLC125

46.8

16.5

General Considerations

1.A generator set needs the engine to deliver 2 hp of energy to the alternator for every 1000 watts of electric output power (example: an 8000 watt generator needs the engine to deliver 16 hp of energy to the generator end).

2.An engine needs 10,000 BTU’s of fuel energy per horsepower of engine power to provide a sufficient supply of fuel (example: a 16 Hp engine needs 160,000 BTU’s of fuel energy for it to work properly). This fuel must be supplied to the regulator on the generator set at a pressure of 6 oz (11 inches of water column). To achieve this 6 oz. pressure in a L.P. System, you will normally have to reduce the tank pressure by means of a primary regulator or a regulator system of 2 or more regulators.

3.There are 2,516 BTU’s in one cubic foot of Propane (LP Fuel). There are 1,096 BTU’s in one cubic foot of Natural Gas.

4.There are 36.39 cubic feet in one gallon of Propane. There are 57.75 cubic feet in one gallon of Natural Gas.

5.There are 8.58 cubic feet per pound of Propane. There are 23.56 cubic feet per pound of Natural Gas.

6.When installing the piping for the gaseous fuel supply please refer to the pipe chart in Tables 3-5 and 3-6 to be sure you are using piping of significantly large size to deliver the necessary amount of fuel.

7.If copper tubing is used, it should be “K” or “L” having a minimum wall thickness of 0.032 inches. Black Iron Pipe is recommended but follow building codes for your area.

The following pamphlets are available from:

National Fire Protection Association (NFPA) P.O. Box 9101 Quincy, MA 02269

No. 37 – Combustion Engines

No. 54 – Gaseous Appliances and piping

No. 58 – Storage and handling LPG

3-6 Receiving & Installation

MN2408

Image 38
Contents GLC Generator California Proposition 65 Warning Table of Contents Generator AC Metering Engine Parameter Display Appendix aSection Product Safety Information Read This Manual ThoroughlySymbols OperationOperation Warning Statements Burn Installation Maintenance Product Safety Information MN2408 Labor Parts Limited WarrantyWarranty Period General Information MN2408 Installation Guidelines Site PlanningExhaust System Controls and Transfer SwitchEngine Cooling System Room AirVibration Isolators Foundation Design Foundation ChecklistSetting The Genset On An Existing Concrete Floor Slab Weight Of The Genset Approximate Weight vs. kW OutputDesigning An Isolated Foundation Calculate Soil Bearing Load SBL CapacityTypical Foundation Installation Approximate Load Bearing Capacities of Various Soil TypesMulti-Engine Installations Exhaust System Exhaust ChecklistSystem Placement Level Of AttenuationExhaust System Calculations Exhaust Piping Cooling System Cooling System Checklist Radiator CoolingCooling System Design Engine Mounted Radiator Cooling Heat ExchangerCooling System Determination Hot Well Installations Remote Radiator Cooling11 Valves & Fittings and Fluid Flow in Pipe Other Considerations 13 Coolant Mixture Air System Air System Checklist Wind BarrierEngine Crankcase Ventilation Transfer Switch Transfer Switch Checklist Transfer Switch LocationBattery Starting System Battery LocationBattery Charger Battery CablesGeneral Information MN2408 When the Generator is installed outdoors Generator LiftingMounting Dimensions Generator MountingSecure the Generator Ventilation TestGuidelines for Exhaust System Hot Exhaust GassesBackpressure must not exceed 20 of water column Page General Considerations Fuel ConnectionsFuel Consumption Natural and LPG Natural Gas Flow Rate Cubic Feet per Hour per Pipe Length Example Determining Pipe Size for Natural GasNatural Gas Connections Example Determining Pipe Size for LPG LP Gas Flow Rate Cubic Feet per Hour per Pipe LengthTransfer Switch Considerations RatingThree Phase WYE and Delta Connections Frame Ground Connection Battery Charger ConsiderationsGeneral Wiring Considerations Page GLC100 Recommended Engine Oil and Battery TypePost Installation Checks GLC125Post Installation Checks Operator Control Panel Digital Engine Controller Only Run SwitchOn when the OFF Switch is used to stop the engine Programming KeysAutomatic Start/Stop Operator Control PanelManual Start/Stop Automatic Fault Shutdown Automatic Mains Failure AMFUtility Normal Condition Utility Power Failure ConditionsUtility Power Restored Load Test Push-button OperationNo Load Test Engine Controller Inputs & Outputs Analog Faults Crank RunSuch as Fuel Rack Solenoids or electronic governors Engine starter motorFront panel keypad push-button Are no active faultsAction Description Display Comments NormalOther time delay functions are Vab Displays the generators output voltage Phase system not applicableGenerator KVA Display Vbc Displays the generators output voltageBattery Voltage/Engine Speed Navigation Hints Main Menu Loop Voltage Calibration Procedure Displayed values Repeat for each phaseSpan Calibration Oil Pressure Engine Temperature & Oil Pressure CalibrationDisplays the type of calibration function UsedConfiguration Data Sheet Main Menu Loop Parameters Parameter Setting Volts A-B Fault Name Input Analog198 F Alarm Battery VoltageEngine Control Connections Operator Control Panel Analog Engine Controller Only 10 Analog Operator Control Panel11 9957N Analog Engine Controller Connections 12 A121H Analog Engine Controller Connections Service Garretson Model KN Fuel Valve Considerations GeneralInstallation Section Troubleshooting and Maintenance EngineProblems and Solutions General Troubleshooting GuideTroubleshooting Guide Digital Controller Only Speed Troubleshooting Guide Analog Controller OnlyVerify the adjustments. Replace controller if failed Part number DIODE, 1N5408LAMP, #67, 12 Volt Replacement PartsGLC GLC125 Flywheel Housing Magnetic Pickup Cable Jam NutGLC Circuit Breaker & Electrical Data FLAGLC Data 259 300 MN2408 Series GLC A-7 144 150 GLC Wire Size Figure A-2 Customer Interface Connection Diagram MN2408 Series GLC A-11 Figure A-4 Single Phase w/o Breaker Connection Diagram Figure A-5 Single Phase One Breaker Connection Diagram Figure A-6 Single Phase Two Breaker Connection Diagram MN2408 Series GLC A-15 Series GLC MN2408 MN2408 Series GLC A-17 Series GLC MN2408 Figure A-11 Three Phase Connection Diagram Figure A-12 Three Phase Connection Diagram with PMG MN2408 Series GLC A-21 Series GLC MN2408 MN2408 Series GLC A-23 Series GLC MN2408 MN2408 Series GLC A-25 Series GLC MN2408 MN2408 Series GLC A-27 Figure A-20 Control Box Connections with MEC2 Controller Figure A-21 Engine Wiring, Woodward 4.3L GM Figure A-22 Engine Wiring, Woodward 5.7L GM Figure A-23 Engine Wiring, Woodward 8.1L GM Series GLC MN2408 Standby Continuous PowerName Address Phone Model Number Job Number No LoadAre legible Adjust the AC voltage to match the normal sourceSwitch Proper belt alignment and tensionsBaldor District Offices Baldor Electric Company MN2408 04 FAR200