Transfer Switch
Transfer Switch Checklist
A.Locate transfer switch in a clean, dry place, near the emergency load.
B.Provide a circuit breaker between the genset and the transfer switch.
C.Put a flexible connection between the conduit and genset.
D.Observe applicable codes in
The transfer switch connects the genset to the emergency power system. The emergency power system may include several gensets and several transfer switches. Typically, the genset is wired to the emergency power system through a transfer switch as shown in Figure 2‐8.
Figure 2‐8 Typical Emergency power System Installations
Multiple Gensets can be arranged either in parallel or separately connected to dedicated emergency loads. Figure 2‐8 also shows a typical arrangement of two gensets in parallel with transfer switches for loads that have different levels of priority. A typical multiple genset installation is shown for NFPA 110 Level 1 and Level 2 emergency power circuits and a priority control to select the appropriate transfer switch.
Wattmeters should be installed on each genset so load sharing can be checked. The control system should include an automatic paralleling control. Paralleling identical gensets is not difficult, but paralleling dissimilar sets can cause load sharing problems. When designing an installation that includes the paralleling of dissimilar generators, contact your nearby Baldor Distributor.
Transfer Switch Location
The transfer switch location is important and key considerations are:
1.Locate the transfer switch as close to the emergency load as practical to avoid interruptions of the emergency power system due to natural or
2.Locate the transfer switch in a clean, dry, well ventilated location, away from excessive heat. When the ambient air is above 104 °F (40 °C), fuses and circuit breakers must be derated. Allow adequate working space around the transfer switch.
3.A circuit breaker (or fuses) should be installed in the line between the generator and the transfer switch. Baldor Gensets are available with properly sized circuit breaker built into the generator control through 1200 amp breakers. The circuit breaker can be separately mounted. In the case of very large circuit breakers, a separate floor mounted circuit breaker is easier to wire up than a wall mounted breaker.
4.Install power and control wires in separate solid conduit with flexible sections at the genset. The flexible sections prevent vibration from damaging the conduit. All power conduits from the genset must contain all three phases.
5.Never install control wires in the same conduit as power conductors.
MN2408 | General Information 2‐11 |