Baldor GLC60 Utility Normal Condition, Utility Power Failure Conditions, Utility Power Restored

Models: GLC40 GLC25 GLC15 GLC100 GLC30 GLC65 GLC20 GLC45 GLC105 GLC60 GLC10

1 114
Download 114 pages 7.44 Kb
Page 56
Image 56

When the controller is applied in an Auto Mains Failure (AMF) application with a transfer switch, it must be wired as shown in Figure 4‐14. Programmable output #3 must be selected for Utility Ready To Load and programmable output #4 must be selected for Gen Ready To Load. After the controller is programmed, the AMF sequence of operation will be as follows:

Utility Normal Condition:

1.Remote Start input signal (terminals 16 & 17) is not activated (i.e. normal).

2.Utility Ready To Load output is energized (i.e. signal to transfer switch to transfer to utility power).

3.Generator Ready To Load output is de-energized.

Utility Power Failure Conditions:

1.Remote Start input signal is activated (i.e. remote start contact closes when utility power fails, as sensed by utility voltage sensor).

2.Engine starts after the Engine Start Delay timer (Utility Ready To Load output stays energized).

3.After the engine has started and the generator output rises above the programmed voltage and frequency limits, a Warm-Up timer is initiated.

4.After the Warm-Up timer expires the Utility Ready to Load output de-energizes and the NEUTRAL Delay timer is initiated.

5.After the NEUTRAL DELAY timer expires the Gen Ready to Load output energizes to signal the transfer switch to transfer to the generator supply. Note: The neutral delay function is only operative with an electrically-held type transfer switch mechanism (ie. electrical contactor type).

Utility Power Restored:

1.Remote Start input signal is removed and the Return Delay timer is initiated (i.e. Utility Voltage returns to normal and the Utility voltage sensor contact opens).

2.After the Return Delay timer expires, the Generator Ready to Load output de-energizes and the Neutral Delay timer is initiated.

3.After the Neutral Delay timer expires the Utility Ready to Load output energizes to signal the transfer switch to transfer to the utility supply. Note: If the generator has a shutdown during the Return or Neutral Delay periods, the timers are bypassed, and the Utility Ready to Load output immediately energizes.

4.The generator Cool down Timer starts after the Return Delay timer.

5.The generator stops after the Cool down Timer.

Load Test Push-button Operation

1.When the Load Test pushbutton is pressed, the logic will internally simulate receiving a remote start input.

2.Engine starts after the Engine Start delay timer.

3.After the engine has started and the generator output rises above the programmed voltage and frequency limits, a Warm-Up timer is initiated.

4.After the Warm-Up timer expires the Utility Ready to Load output de-energizes and the Neutral Delay timer is initiated.

5.After the Neutral Timer expires the Gen Ready To Load output energizes to signal the transfer switch to transfer to the generator supply.

Note: If a generator shutdown occurs during a Load Test Operation, the Load Test mode will be de-activated.

When Auto Mode is restored (after Load Test Operation) the following occurs:

1.Simulated Remote Start input signal is removed.

2.Gen Ready To Load output de-energizes, and Neutral Delay timer is initiated.

3.After the Neutral Delay timer expires The Utility Ready To Load output energizes to signal the transfer switch to transfer to the utility supply.

4.The generator Cool down timer starts timing following the transfer to the utility supply.

5.The generator stops after the Cool down timer.

4‐16 Operation

MN2408

Page 56
Image 56
Baldor GLC60, GLC105, GLC45, GLC20 Utility Normal Condition, Utility Power Failure Conditions, Utility Power Restored