4.Reattach the ramps to the pallet.

5.Replace the plastic antistatic bag and foam inserts.

6.Replace the cardboard surrounding the cabinet.

7.Replace the cardboard caps.

8.Secure the assembly to the pallet with straps.

The cabinet is now ready for shipment.

Setting Up the System

After a site is prepared, the system is unpacked, and all components are inspected, the system can be prepared for booting.

Moving the System and Related Equipment to the Installation Site

Carefully move the cabinets and related equipment to the installation site but not into the final location. If the system is to be placed at the end of a row, you must add side bezels before positioning the cabinet in its final location. Check the path from where the system was unpacked to its final destination to make sure the way is clear and free of obstructions.

WARNING! If the cabinet must be moved up ramps, be sure to maneuver it using three people.

Unpacking and Installing the Blower Housings and Blowers

Each cabinet contains two blower housings and four blowers. Although similar in size, the blower housings for each cabinet are not the same; one has a connector to which the other attaches. To unpack and install the housings and blowers, follow these steps:

1.Unpack the housings from the cardboard box and set them aside.

The rear housing is labeled Blower 3 Blower 2. The front housing is labeled Blower 0 Blower 1.

CAUTION: Do not lift the housing by the frame (Figure 3-12).

Figure 3-12 Blower Housing Frame

72 Installing the System

Page 72
Image 72
HP Integrity Superdome and 9000 Superdome sx2000 manual Setting Up the System