IBM 4QX, 9TX, 9TS, 9QX, 9QS, 900, 4SB, 4SA, 42P, 42X, 200, 42E, 42S Installing the vertical mounting plate

Models: 4QX 42S 4SA 900 42X 42P 9TX 200 9QS 9QX 4QS 4SB 9TS 42E

1 208
Download 208 pages 9.56 Kb
Page 167
Image 167

Figure 69. Installing the Rack PDU on the vertical mounting plate

3.Install the vertical mounting plate in the side of your rack cabinet with four M6 screws and nuts that come with this option. Make sure that the three-connector side of the Rack PDU is facing up.

Figure 70. Installing the vertical mounting plate

4.Route the fixed line cord down, towards the rack side braces; then, route the line cord along the side brace towards the back of the rack cabinet and secure it with the cable straps that come with this option.

NetBAY Power Distribution Units 159