Testing
Ending an Active Test
Except for the Remote Send Line Loopback and Remote DCLB, a test initiated by the user can be ended by the user. Tests can also be terminated automatically by enabling the Test Timeout option from the System Options Menu.
HA Test Timeout option is available to automatically terminate a
Test Timeout does not pertain to tests initiated by the network.
HOn each test screen is a Command column. To stop the test, press Enter when the cursor is on the Stop command.
HUse the Abort All Tests selection from the Test menu to stop all tests running on all interfaces, with the exception of
An aborted test may continue to run for a few seconds as the abort command is sent to the remote end and processed.