Maintenance and repairs 11.2 Safety guidelines for
11.2Safety guidelines for high-voltage test
Guidelines for inspecting the insulation resistance
WARNING
An insulation resistance inspection under
If insulation resistance inspections need to be carried out on a machine/plant with direct drives or directly on the motors (e.g. installation inspection, preventative maintenance, troubleshooting), only inspection devices that comply with EN
The inspection may only be carried out with a maximum direct voltage of 1000 V for a maximum time of 60 s! The test voltage should be measured with respect to ground or the motor enclosure. If a higher DC or AC voltage is necessary for the purposes of inspecting the machine/system, you must arrange the inspection with your local Siemens office.
Please follow the operating instructions for the test device!
Inspections of the insulation resistance on individual motors must always be carried out as follows:
1.Connect all winding and temperature sensor connectors with each other; inspection voltage not to exceed 1000 VDC, 60 s against PE connection.
2.Connect all temperature sensor connectors to the PE connector and all winding connectors with each other; the inspection voltage must not exceed 1000 VDC, 60 s, winding against PE connector.
Each insulation resistance must be at least 10 MΩ, otherwise the motor insulation is defective.
11.3Maintenance
Performing maintenance work on the motor
WARNING
Note the safety information provided in this documentation.