Basic Installation Procedure

This section provides the basic steps that you need to perform when installing InfraStruXure power and rack components. Follow the references provided with each step for detailed instructions.

Do not begin installing your InfraStruXure system without an APC Field Service Engineer present.

Warning

1.Unpack the components according to the unpacking instructions included on the outside of the packaging or in the installation manual included with the component.

Search all boxes and packaging to make sure that they are empty before discarding.

Note

2.Determine the correct placement of your system components by studying your InfraStruXure Configure-To-Order (CTO) Report. Move the Symmetra PX UPS, InfraStruXure PDU, RDP, Battery Enclosure, and NetShelter VX Enclosures to their final location.

If installing InfraStruXure on a raised floor, make sure that the raised- floor structure has a lb/in2 rating that will support the full weight of the

Warning InfraStruXure installation. See “Weight Considerations” on page 9.

3.Level the PDU, UPS, RDP, NetShelter, and Battery Enclosures, using the 13/14-mm wrench included with each unit.

See page 18 for detailed instructions.

4. Exchange side panels and run battery communication cables.

See page 20 for detailed instructions.

5. Join adjacent enclosures.

For instructions on joining the PDU, UPS, and Battery Enclosure see page 22.

For instructions on joining to RDP to a NetShelter VX Enclosure, or joining adjacent NetShelter VX Enclosures, see the installation manual included with

See also your enclosures.

6. Ensure total power off.

See page 23 for detailed instructions.

14

InfraStruXure System—Installation and Start-Up

Page 24
Image 24
American Power Conversion InfraStruXureTM System manual Basic Installation Procedure