Start-Up Procedure: InfraStruXure System
4.Set the UPS System Enable switch to the OFF position.
5. Set the Battery Enclosure DC Disconnect circuit breaker to the OFF position.
Verify proper voltage and phase rotation on the PDU
1. Close (turn ON) the Q1 circuit breaker on the InfraStruXure PDU to apply power to the UPS.
2.Ensure
3.Verify proper voltage is present at the UPS input bus bars (208V, metered
4.Ensure
5.Verify proper voltage is present at the top of the PDU bypass switch (208V, metered
The voltage for the bypass feed can only be 208V,
Warning